1 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF September 18, 2006 |
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | |||||||||
Domestic Deepwater Semisubmersibles (7) | ||||||||||||||||||
Ocean Quest | 3,500’ | GOM | Contracted | Noble | one year term + option | low 270’s | mid April 2006 | mid April 2007 | Two-year term, plus option,** with Noble in mid 350’s beginning mid-April 2007 and ending mid-April 2009. Available; actively marketing. | |||||||||
Ocean Star | 5,500’ | GOM | Contracted | Anadarko | one year term + option | mid 170’s | mid Nov. 2005 | mid Oct. 2006 | One-year term extension with Anadarko, plus option,** in mid 380’s beginning mid Oct. 2006 and ending mid Oct. 2007; followed by one-year term extension, plus option, with Anadarko in mid $410’s beginning in mid Oct. 2007 and ending in mid Oct 2008. Available; actively marketing. | |||||||||
Ocean America | 5,500’ | GOM | Contracted | Mariner | Mariner one year term | low 230’s | mid April 2006 | mid April 2007 | One year extension from Mariner in low 400’s beginning mid April 2007 and ending mid April 2008. Available; actively marketing. | |||||||||
Ocean Valiant | 5,500’ | GOM | Contracted | Anadarko | one year term | low 300’s | mid Mar. 2006 | mid Mar. 2007 | One-year term extension with Anadarko, plus option,** in mid 390’s beginning mid Mar. 2007 and ending mid Mar. 2008; followed by one-year term extension with Anadarko in mid $420’s beginning mid Mar. 2008 and ending mid Mar. 2009. Available; actively marketing. | |||||||||
Ocean Victory | 5,500’ | GOM | Contracted | Murphy | one year term | mid 200’s | early Dec. 2005 | early Dec. 2006 | Two-year term extension plus option** with Murphy in mid 320’s beginning early Dec. 2006 and ending early Dec. 2008. Available; actively marketing. | |||||||||
Ocean Baroness | 7,000’ | GOM | Contracted | Amerada Hess | one year term | low 200’s | mid Nov. 2005 | late Dec. 2006 | Three-year term extension with Amerada Hess, plus option,** in mid 360’s beginning late Dec. 2006 and ending late Dec. 2009. Available; actively marketing. | |||||||||
Ocean Confidence | 7,500’ | GOM | Contracted | BP | two year term plus option | low 280’s | early Jan. 2006 | early Jan. 2008 | Approximately 21 days maintenance beginning early Sept. and ending late Sept. Available; actively marketing. | |||||||||
Domestic 2nd/3rd Generation Semisubmersibles (6) | ||||||||||||||||||
Ocean New Era | 1,500’ | GOM | Contracted | W&T | three wells | low 250’s | early Sept. 2006 | late Nov. 2006 | Remainder of 225 day term with Walter in mid 130’s beginning late Nov. 2006 and ending late Feb. 2007 Available; actively marketing. | |||||||||
Ocean Whittington | 1,500’ | GOM | DODI | - | Survey and Maintenance | - | - | - | Special survey and maintenance approximately 150-180 days beginning in mid July 2006 and ending in late Jan. 2007. Available; actively marketing. | |||||||||
Ocean Voyager | 2,000’ | GOM | DODI | - | Survey and Maintenance | - | - | - | Approximately 38 days maintenance beginning late Aug. and ending late Sept.; followed by one assignment well from Hess to Marathon in low 300’s beginning late Sept. and ending late Nov.; followed by one well with Walter in low 80’s (transferred from prior Lexington contract) beginning late Nov. 2006 and ending early Jan. 2007. Available; actively marketing. | |||||||||
Ocean Concord | 2,200’ | GOM | Contracted | Anadarko | one well | mid 90’s | late June 2006 | mid Sept. 2006 | One well with Pogo (moved from Lexington) in low 200s beginning in mid Sept. and ending in mid Oct.; followed by remainder of 90-day term extension with Tana in low 130’s; followed by new 90-day term extension with Tana, plus option,** in low 170’s beginning mid Dec. and ending mid Mar. 2007; followed by additional 90-day extension with Tana, plus option,** in low 270’s beginning mid Mar. 2007 and ending mid June. Available; actively marketing. | |||||||||
Ocean Lexington | 2,200’ | GOM | Contracted | BP | prep | low 250’s | late Aug. 2006 | late Sept. 2006 | Approximately 30 day prep followed by approximately 75-day fully-paid mobe to Egypt for 36-month term with BP in mid 260’s ending late Aug. 2009. Available; actively marketing. | |||||||||
Ocean Saratoga | 2,200’ | GOM | DODI | - | Survey and Maintenance | - | - | - | Special survey and maintenance (approximately 160 days) beginning late July and ending early Feb. 2007; followed by six-month extension, plus option,** in low 120’s with LLOG beginning early Jan. 2007 and ending early July 2007. Available; actively marketing. |
2 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF September 18, 2006 |
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | |||||||||
Domestic Jackups (10) | ||||||||||||||||||
Ocean Crusader | 200’ MC | GOM | Contracted | Walter | three wells | low 80’s | mid May 2006 | late Nov. 2006 | Six month term, plus option,** with Energy Partners in high $110’s beginning late Nov. 2006 and ending late May 2007. Available; actively marketing. | |||||||||
Ocean Drake | 200’ MC | GOM | Contracted | Chevron | term contract | mid 100’s | late June 2006 | mid Oct. 2006 | Indexed term contract. Six-month term extension plus option beginning mid Oct. 2006 and ending late Mar. 2007. Available; actively marketing. | |||||||||
Ocean Champion | 250’ MS | GOM | Contracted | Apache | one well | high 90’s | mid Sept. 2006 | mid Oct. 2006 | Third of three wells with Apache in mid 100’s beginning mid Oct. 2006 and ending late Dec. 2006. Available; actively marketing. | |||||||||
Ocean Columbia | 250’ IC | GOM | Contracted | Newfield | one year term plus option | low 120’s | early Aug. 2006 | early Aug. 2007 | Available; actively marketing. | |||||||||
Ocean Spartan | 300’ IC | GOM | Contracted | Hunt | three wells | mid 100’s | early July 2006 | late Sept. 2006 | Available; actively marketing. | |||||||||
Ocean King | 300’ IC | GOM | Contracted | El Paso | one year term | mid 110’s | early Mar. 2006 | early Mar. 2007 | Available; actively marketing. | |||||||||
Ocean Nugget | 300’ IC | GOM | DODI | - | mobe for Pemex | — | — | — | 912-day term with Pemex in high 160’s beginning late Sept. 2006 and ending early Mar. 2009. Available; actively marketing. | |||||||||
Ocean Summit | 300’ IC | GOM | DODI | - | Survey and Maintenance | - | - | - | Approximately 42-day survey rescheduled to begin mid Sept. Available; actively marketing. | |||||||||
Ocean Titan | 350’ IC | GOM | Contracted | Dominion | six month term | high 70’s | early Feb. 2006 | midOct. 2006 | Available; actively marketing. | |||||||||
Indexed term contractwith floor in low | ||||||||||||||||||
Ocean Tower | 350’ IC | GOM | Contracted | Chevron | two year term extension + option | mid140’s | late April 2006 | late April 2008 | 140’s and ceiling in low 200’s. Available; actively marketing. | |||||||||
International Semisubmersibles (16) | ||||||||||||||||||
MEXICO | ||||||||||||||||||
Ocean Ambassador | 1,100’ | GOM | Contracted | PEMEX | four year term work | mid 50’s | late July 2003 | mid Dec. 2007 | Available; actively marketing. | |||||||||
Ocean Worker | 3,500’ | GOM | Contracted | PEMEX | four year term work | high 60’s | mid Aug. 2003 | late July 2007 | Approximately 30-day survey and prep beginning late July 2007 and ending late Aug. 2007; followed by six-month term with Petro-Canada in Trinidad in the low $450’s plus mobe/demobe beginning late Aug. 2007 and ending late Mar. 2008. Available; actively marketing. | |||||||||
Ocean Yorktown | 2,850’ | GOM | Contracted | PEMEX | four year term work | mid 40’s | late Oct. 2003 | mid July 2007 | Available; actively marketing. | |||||||||
NORTH SEA | ||||||||||||||||||
Ocean Nomad | 1,200’ | North Sea | Contracted | Talisman | one year | high 150’s | early Feb. 2006 | early Feb. 2007 | 18-month extension with Talisman in mid 280’s beginning early Feb. 2007 and ending early Aug. 2008; followed by LOI for two-year term in mid 330’s beginning early Aug. 2008 and ending early Aug. 2010. Available; actively marketing. | |||||||||
Ocean Guardian | 1,500’ | North Sea | Contracted | Shell | one year | low 160’s | late Mar. 2006 | late Mar. 2007 | Available; actively marketing. | |||||||||
Ocean Princess | 1,500’ | North Sea | Contracted | Talisman | two year term | mid 150’s | late Jan. 2006 | late Jan. 2008 | Two-year term extension with Talisman in mid 330’s beginning late Jan. 2008 and ending late Jan. 2010. Available; actively marketing. | |||||||||
Ocean Vanguard | 1,500’ | North Sea | Contracted | Statoil | term | low 140’s | late May 2005 | mid Oct. 2006 | Two six-month options with Statoil exercised in mid 160’s beginning mid Oct. 2006 and ending mid Oct. 2007. Remaining six-month option priced in mid 160’s exercised beginning mid Oct. 2007 and ending mid April 2008; followed by two year extension with Statoil in low 400’s beginning mid April 2008 and ending mid April 2010. Available; actively marketing. |
3 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF September 18, 2006 |
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | |||||||||
AUSTRALASIA | ||||||||||||||||||
Ocean Bounty | 1,500’ | Australia | Contracted | Santos | two wells | mid 90’s | late June 2006 | late Sept. 2006 | Four wells in high 90’s with Woodside beginning late Sept. 2006 and ending mid April 2007; followed by four well extension in mid 100’s beginning mid April 2007 and ending early Nov. 2007; followed by one-year term with Woodside in low 350’s beginning early Nov. 2007 and ending early Dec. 2008(term to include approximately 30-day survey beginning mid April 2008 and ending mid May 2008). Available; actively marketing. | |||||||||
Ocean Patriot | 1,500’ | Australia | Contracted | Nexus | one assignment well from Apache | mid 80’s | mid July 2006 | lateSept. 2006 | One well with Tap Oil in upper 70’s beginninglateSept. and ending late Oct. 2006; followed by last option well exercised with Anzon in low 350’s beginning late Oct. 2006 and ending late Nov. 2006; followed by four wells, plus option,** with NZOP in low 100’s, beginning late Nov. 2006 and ending mid May 2007; followed by LOI for one-year term in mid 370’s beginning in mid May 2007 and ending in mid May 2008. Available; actively marketing. | |||||||||
Ocean Epoch | 1,640’ | Malaysia | Contracted | Shell | term program | mid 220’s | early April 2006 | early Nov. 2006 | 12-well program with Shell in Australia in mid 220’s beginning early Nov. 2006 and ending early Dec. 2007. Available; actively marketing. | |||||||||
Ocean General | 1,640’ | Vietnam | Contracted | Premier | one well | mid 150’s | mid Sept. 2006 | mid Oct. 2006 | One assignment well with Idemitsu Vietnam in mid 170’s beginning mid Oct. and ending mid Nov. 2006;followed by approximately two-week survey and maintenance beginning late Nov. 2006 and ending mid Dec. 2006; followed by three wells with Inpex in Indonesia in mid 130’s beginning late Nov. 2006 and ending mid June 2007; followed by two additional wells with Inpex in mid 170’s beginning mid June 2007 and ending mid Aug. 2007; followed by two additional assignment wells from Inpex with Total in mid 170’s beginning mid Aug. and ending early Oct. 2007. Available; actively marketing. | |||||||||
Ocean Rover | 7,000’ | Malaysia | Contracted | Murphy | 950 day extension | mid 170’s | late June 2005 | mid Jan. 2008 | Available; actively marketing. | |||||||||
BRAZIL Ocean Yatzy | 3,300’ | Brazil | Contracted | DODI | UWILD & maintenance | - | late Aug. 2006 | late Sept. 2006 | Resume four-year extension, plus potential bonus, in mid 110’s ending early Oct. 2009. Available. | |||||||||
Ocean Winner | 3,500’ | Brazil | Contracted | Petrobras | 700 day extension | low 110’s | mid Mar. 2006 | mid Mar. 2010 | Available. | |||||||||
Ocean Alliance | 5,000’ | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 150’s | early Sept. 2005 | early Sept. 2009 | Available. | |||||||||
International Drillships (1) | ||||||||||||||||||
Ocean Clipper | 7,500’ | Brazil | Contracted | Petrobras | five year extension plus potential bounus | low 180’s | mid Dec. 2005 | mid Dec. 2010 | Available. | |||||||||
International Jackups (3) | ||||||||||||||||||
Ocean Spur | 300’ IC | Tunisia | Contracted | Soco Tunisia | one year term | mid 120’s | mid March 2006 | mid March 2007 | LOI for 180-day term in mid 160’s in Egypt beginning mid Mar. 2007 and ending mid Sept. 2007. Available; actively marketing. | |||||||||
Ocean Sovereign | 300’ IC | Indonesia | Contracted | Kodeco | one well | mid 80’s | mid Sept. 2006 | mid Oct. 2006 | 18-month term with Kodeco in mid 90’s beginning mid Oct. 2006 and ending late Mar. 2008. Available; actively marketing. | |||||||||
Ocean Heritage | 300’ IC | Qatar | Contracted | Maersk | one year term | low 140’s | early May 2006 | mid June 2007 | Program to include approximately 45 day special survey and maintenance beginning early Oct. 2006 and ending mid Nov. 2006. Available; actively marketing. |
4 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF September 18, 2006 |
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | |||||||||
Upgrade (2) | ||||||||||||||||||
Ocean Endeavor | 2,000’ | Shipyard | Upgrading | DODI | - | - | - | - | Singapore shipyard for upgrade to 10,000 ft. capable 5th Generation rig. Estimated completion early 2007; followed by commissioning beginning early Mar. 2007; followed by four year term with Devon in low 250’s. Available; actively marketing. | |||||||||
Ocean Monarch | 2,200’ | Shipyard | Upgrading | DODI | - | - | - | - | Singapore shipyard for upgrade to 10,000 ft. capable 5th Generation rig. Estimated completion, including commissioning, fourth quarter 2008; followed by four-year term, plus mobe, plus option, with Anadarko in the GOM in the mid $420’s beginning late Dec. 2008 and ending late Dec. 2012. Available; actively marketing. | |||||||||
New-build Rigs Under Construction (2) | ||||||||||||||||||
Ocean Shield | 350’ IC | Shipyard | - | - | - | - | - | - | Singapore shipyard, estimated completion Q1 2008; followed by LOI for one-year term in Australia in mid 260’s beginning upon delivery in the first quarter of 2008. Available; actively marketing. | |||||||||
Ocean Scepter | 350’ IC | Shipyard | - | - | - | - | - | - | Brownsville shipyard, estimated completion Q1 2008. Available; actively marketing. |