8-K Filing
Diamond Offshore Drilling (DODRW) 8-KRegulation FD Disclosure
Filed: 20 Jan 09, 12:00am
RECENT COMMITMENTS — (See Body of Report For Contract Details/Date Changes and Other Information) | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||||
Domestic Deepwater Semisubmersibles (8) | ||||||||||||||||||
Ocean Quest | 3,500’ | GOM | Current Contract | Noble | two-year term + unpricedoption | upper 350’s | mid June 2007 | early Feb. 2009 | ||||||||||
GOM/Brazil | Prep, mobe & acceptance test for ENI Brasil/OGX | ENI/OGX | 0 | early Feb. 2009 | early May 2009 | |||||||||||||
Brazil | Future Contract | ENI Brasil | 150 day assignment from Noble | mid 380’s | early May 2009 | early Oct. 2009 | ||||||||||||
Brazil | Future Contract | OGX | two-year term + unpricedoption | low 420’s | early Oct. 2009 | early Oct. 2011 | ||||||||||||
Ocean Star | 5,500’ | GOM | Current Contract | Anadarko | term extension | upper 410’s | early Nov. 2007 | lateJan 2009 | ||||||||||
GOM | Future Contract (swap from oldVictory/Voyager contract in low 300’s) | Newfield | one well | low 300’s | lateJan. 2009 | lateMarch 2009 | ||||||||||||
GOM | Future Contract (swap fromVictory contract) | Newfield | one well extension | low 500’s | lateMarch 2009 | early May 2009 | ||||||||||||
Ocean America | 5,500’ | GOM | Current Contract | Mariner | term | mid 460’s | late Oct. 2008 | mid July 2009 | ||||||||||
GOM | Special Survey & Maintenance | DODI | 0 | late Jan. 2009 | early May 2009 | |||||||||||||
GOM | Future Contract | Mariner | 1-year term; convertible to 6-month term (ending Jan. 2010) in low 550’s w/notice by 1-Feb. 09 | low 530’s | lateJuly 2009 | lateJuly 2010 | ||||||||||||
Ocean Valiant | 5,500’ | GOM | Current Contract | Anadarko | one-year term extension | upper 420’s | mid Dec. 2008 | late July 2009 | ||||||||||
Mobe | Lump sum mobe | DODI | late July 2009 | late Sept. 2009 | ||||||||||||||
Angola | Future Contract | Total | two-year term +priced options | low 620’s | late Sept. 2009 | late Sept. 2011 | ||||||||||||
Ocean Victory | 5,500’ | GOM | Current Contract | Noble Energy | one well + unpriced option | mid 370’s | early Jan. 2009 | early March 2009 | ||||||||||
GOM | Future Contract | ATP | one-year term, minimum | low 540’s | early March 2009 | early March 2010 | ||||||||||||
Ocean Baroness | 7,000’ | GOM | Current Contract | Hess | term extension +unpricedoption | mid 360’s | late Nov. 2007 | mid April 2010 | ||||||||||
Ocean Confidence | 10,000’ | GOM | Current Contract | Murphy | four-year term + unpricedoption | upper500’s | late Feb. 2008 | late March 2012 | ||||||||||
GOM | Maintenance | DODI | 0 | mid Feb. 2009 | late Feb. 2009 | |||||||||||||
Ocean Endeavor | 10,000’ | GOM | Current Contract | Devon | four-year term + unpriced option | mid 290’s | early July 2007 | late June 2011 | ||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||||
Domestic 2nd and 3rd Generation Semisubmersibles (2) | ||||||||||||||||||
Ocean Ambassador | 1,100’ | GOM | Current Contract | Taylor | seven-month term | mid 280’s | late Dec. 2008 | mid May 2009 | ||||||||||
GOM/Brazil | Prep, mobe & acceptance test for OGX | OGX | 0 | mid May 2009 | early Sept. 2009 | |||||||||||||
Brazil | Future Contract | OGX | three-year term + unpricedoption | low 260’s | early Sept. 2009 | early Sept. 2012 | ||||||||||||
Ocean Saratoga | 2,200’ | GOM | Current Contract | Walter | five wells | mid 280’s | early Dec. 2008 | early May2009 | ||||||||||
GOM | Future Contract | Taylor | 16-month term +unpriced option | mid 280’s | early May2009 | mid July 2010 | ||||||||||||
Domestic Jack-ups (7) | ||||||||||||||||||
Ocean Crusader | 200’ MC | GOM | Current Contract | Walter | two wells | mid 70’s | mid Oct. 2008 | midFeb. 2009 | ||||||||||
Ocean Drake | 200’ MC | GOM | Current Contract | Tarpon | one well | mid 60’s | late Oct. 2008 | lateJan. 2009 | ||||||||||
GOM | Future Contract | Tarpon | two wells | mid 70’s | lateJan. 2009 | lateMarch 2009 | ||||||||||||
Ocean Champion | 250’ MS | GOM | Current Contract | Stone | six months + unpricedoption | low 70’s | late Oct. 2008 | late April 2009 | ||||||||||
Ocean Spartan | 300’ IC | GOM | Future Contract | Samson | two-well extension, part 2 | low 120’s | mid Dec. 2008 | earlyFeb. 2009 | ||||||||||
Ocean Summit | 300’ IC | GOM | Actively Marketing | DODI | ||||||||||||||
Ocean Titan | 350’ IC | GOM | Current Contract | Apache | third of three wells | low 110’s | mid Nov. 2008 | lateJan. 2009 | ||||||||||
GOM | Future Contract | Apache | four-month extension + unpricedoption | low 130’s | lateJan. 2009 | lateMarch 2009 | ||||||||||||
GOM | Special Survey and Maintenance | DODI | 0 | lateMarch 2009 | late April 2009 | |||||||||||||
GOM | Future Contract | Apache | resume four-month extension | low 130’s | late April 2009 | late June 2009 | ||||||||||||
Ocean Tower | 350’ IC | GOM | Hurricane Ike Repairs | DODI | mid Oct. 2008 | early Oct. 2009 | ||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||||
International Semisubmersibles (19) | ||||||||||||||||||
MEXICO | ||||||||||||||||||
Ocean New Era | 1,500’ | GOM | Current Contract | PEMEX | 2 1/2 year term | mid 260’s | late Oct. 2007 | mid Feb. 2010 | ||||||||||
Ocean Voyager | 3,000’ | GOM | Current Contract | PEMEX | 2 1/2 year term | mid 330’s | early Nov. 2007 | late Feb. 2010 | ||||||||||
NORTH SEA/MEDITERRANEAN | ||||||||||||||||||
Ocean Nomad | 1,200’ | North Sea | Current Contract | Talisman | resume two-year term extension | mid 330’s | late Oct. 2008 | late Sept. 2010 | ||||||||||
Ocean Guardian | 1,500’ | North Sea | Current Contract in Administration | Oilexco | Standby in Invergordon | |||||||||||||
North Sea | Future Contract in Administration | Nippon | sublet from Oilexco | low 350’s | early April 2009 | early June 2009 | ||||||||||||
North Sea | Future Contract in Administration | Oilexco | resume two-year term | low 350’s | early June 2009 | mid July 2009 | ||||||||||||
North Sea | Future Contract in Administration | Oilexco | two-year term extension including approx. 50 day survey and maintenance | mid 380’s | mid July 2009 | early Sept. 2011 | ||||||||||||
Ocean Princess | 1,500’ | North Sea | Current Contract | Talisman | resume two-year term extension | upper 330’s | late Dec. 2008 | mid April 2010 | ||||||||||
Ocean Vanguard | 1,500’ | North Sea | Current Contract | Statoil | two-year term extension + unpricedoption | mid 400’s | late April 2008 | mid April 2010 | ||||||||||
Ocean Lexington | 2,200’ | Egypt | Current Contract | BP | 36-month term | mid 260’s | late Nov. 2006 | mid Aug.2009 | ||||||||||
Egypt/Brazil | Prep, mobe & acceptance test for OGX | OGX | 0 | mid Aug. 2009 | late Jan. 2010 | |||||||||||||
Brazil | Future Contract | OGX | three-year term + unpricedoption | mid 330’s | late Jan. 2010 | late Jan. 2013 | ||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||||
AUSTRALASIA | ||||||||||||||||||
Ocean Bounty | 1,500’ | Australia | Current Contract | Woodside | continue one-year term | low 350’s | early Sept. 2008 | late March 2009 | ||||||||||
Australia | Future Contract | Woodside | 60 days | mid 380’s | late March 2009 | late May 2009 | ||||||||||||
Australia | Re-engine and upgrade | DODI | 0 | late May 2009 | to be determined followed by two-year term | |||||||||||||
Australia | Future Contract | Woodside | two-year term | mid 420’s | to be determined | to be determined | ||||||||||||
Ocean Patriot | 1,500’ | Australia | Current Contract | Apache | one-year term | upper 370’s | mid May 2008 | lateJan. 2009 | ||||||||||
Australia | Future Contract | Apache | two-year term + unpricedoption | between 380-420 | lateJan. 2009 | lateJan. 2011 | ||||||||||||
Ocean Epoch | 1,640’ | Australia | Current Contract | Apache | one-year term | mid 350’s | early March 2008 | early March 2009 | ||||||||||
Australia | Future Contract | BHPB | 550-day term + unpricedoptions | low 350’s | early March 2009 | early Sept. 2010 | ||||||||||||
Ocean General | 2,400’ | Vietnam | Current Contract | PVEP | Approx. two-year term + unpricedoptions | low 280’s | mid Oct. 2008 | late Oct. 2010 | ||||||||||
Ocean Rover | 7,000’ | Malaysia | Current Contract | Murphy | balance previously declared option wells | high 240’s | mid Oct. 2008 | early Feb. 2009 | ||||||||||
Malaysia | Future Contract | Newfield | one well | low 450’s | early Feb. 2009 | late March 2009 | ||||||||||||
Malaysia | Future Contract | Murphy | two-year term extension | low 450’s | lateMarch 2009 | lateMarch 2011 | ||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||||
BRAZIL | ||||||||||||||||||
Ocean Whittington | 1,500’ | Brazil | Contract interrupted to resume and complete contract upgrade work | DODI | 0 | mid Oct. 2008 | late Jan. 2009 resume contract | |||||||||||
Brazil | Current Contract | Petrobras | resume five-year term plus potential 15% bonus | mid 220’s | lateJan. 2009 | late Aug. 2012 | ||||||||||||
Ocean Concord | 2,200’ | Brazil | Contract interrupted for survey and to complete contract upgrade work | DODI | 0 | early Jan. 2009 | late Feb. 2009 | |||||||||||
Brazil | Current Contract | Petrobras | resume five-year term plus potential 15% bonus | low 230’s | early Jan. 2008 | early Jan. 2013 | ||||||||||||
Ocean Yorktown | 2,850’ | Brazil | Current Contract | Petrobras | five-year term plus potential 15% bonus | mid 230’s | mid Aug. 2008 | mid Aug. 2013 | ||||||||||
Ocean Yatzy | 3,300’ | Brazil | Current Contract | Petrobras | four-year term extension plus potential 17% bonus | mid 110’s | early Oct. 2005 | early Oct. 2009 | ||||||||||
Brazil | Contract interrupted for 5-year survey | DODI | 0 | late June 2009 | mid Aug. 2009 | |||||||||||||
Brazil | Future Contract | Petrobras | five-year term plus potential 10% bonus | mid 240’s | early Oct. 2009 | early Oct. 2014 | ||||||||||||
Ocean Winner | 3,500’ | Brazil | Current Contract | Petrobras | four-year term extension plus potential 5% bonus | low 110’s | mid March 2006 | mid March 2010 | ||||||||||
Brazil | Future Contract | Petrobras | five-year term extension plus potential 10% bonus | low 270’s | mid March 2010 | mid March 2015 | ||||||||||||
Ocean Worker | 3,500’ | Brazil | Current | DODI | prep., plus acceptance testing | 0 | late July 2008 | late Jan. 2009 | ||||||||||
Brazil | Future Contract | Petrobras | six-year term plus potential 10% bonus | low 270’s | late Jan. 2009 | late Jan. 2015 | ||||||||||||
Ocean Alliance | 5,000’ | Brazil | Future Contract | Petrobras | resume four-year extension plus 20% potential bonus | mid 150’s | early Jan. 2009 | mid June 2010 | ||||||||||
Brazil | Future Contract | Petrobras | six-year term extension plus potential 15% bonus | low 340’s | mid June 2010 | mid June 2016 | ||||||||||||
International Drillship (1) | ||||||||||||||||||
Ocean Clipper | 7,000’ | Brazil | Current Contract | Petrobras | five-year extension plus potential 5% bonus | low 180’s | mid Dec. 2005 | mid Dec. 2010 | ||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||||
International Jack-ups (8) | ||||||||||||||||||
Ocean Columbia | 250’ IC | Mexico | Current Contract | Pemex | 1 1/2-year term | mid 120’s | late Jan. 2008 | mid June 2009 | ||||||||||
Mexico | Intermediate Survey | DODI | 0 | mid June 2009 | early July 2009 | |||||||||||||
Ocean Nugget | 300’ IC | Mexico | Current Contract | Pemex | term contract | upper 160’s | early Oct. 2006 | late March 2009 | ||||||||||
Ocean King | 300’ IC | Croatia | Current Contract | CROSCO | two-year bareboat charter | upper 100’s | mid Nov. 2007 | early Nov. 2009 | ||||||||||
Ocean Sovereign | 300’ IC | Singapore | Intermediate Survey & upgrade | DODI | 0 | late Dec. 2008 | mid Feb. 2009 | |||||||||||
Indonesia | Future Contract | Kodeco | 15-month extension + unpricedoption | mid 140’s | mid Feb. 2009 | mid April 2010 | ||||||||||||
Ocean Heritage | 300’ IC | Gulf of Suez | Current Contract | IPR | seven-month term | mid 110’s | mid July 2008 | late Jan. 2009 | ||||||||||
Ocean Spur | 300’ IC | Egypt | Current Contract | WEPCO | one-year term | low 140’s | mid Aug. 2008 | late Aug. 2009 | ||||||||||
Ocean Shield | 350’ IC | Enroute | Current Contract | ENI | mobe to Australia followed by term | 0 | late Dec. 2008 | late Jan. 2009 | ||||||||||
Australia | Future Contract | ENI | term | mid 260’s | late Jan. 2009 | early Jan. 2010 | ||||||||||||
Ocean Scepter | 350’ IC | Argentina | Current Contract | Enap Sipetrol/YPF | 300-day term contract + unpriced option | high 190’s | late Sept. 2008 | late July 2009 | ||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||
Upgrade (1) | ||||||||||||||||
mobe to GOM and | ||||||||||||||||
Ocean Monarch | 10,000 | Enroute | Current | DODI | prep for contract | 0 | mid Dec. 2008 | early March 2009 | ||||||||
four-year term + | ||||||||||||||||
GOM | Future Contract | Anadarko | unpricedoption | mid 430’s | early March 2009 | early March 2013 | ||||||||||
Actual Oct. 1 — Dec. 31 Down Days | # Days | |||
Rig | Q4 Actual | Comments | ||
Shipyard Time | ||||
Princess | 59 | 5-year survey and maintenance | ||
Ambassador | 90 | 5-year survey and maintenance | ||
Valiant | 73 | 5-year survey/replace derrick and other maint. | ||
Nomad | 36 | 5-year survey and maintenance | ||
Concord | 17 | 5-year survey and maintenance (started early) | ||
Drake | 31 | 5-year survey and maintenance | ||
Rover | 16 | 5-year survey and maintenance | ||
322 | ||||
Other Downtime | ||||
Worker | 92 | Prep for contract, accpt. test | ||
Tower | 92 | Equipment repair (Hurricane Ike damage) | ||
Whittington | 80 | Complete contract upgrade | ||
264 | ||||
2008 Q4 | 586 | |||
Total 2008 | 1,697 | |||
New-build/Upgrade Downtime | ||||
Monarch | 92 | Commission, mobe to U.S. GOM | ||