Diamond Offshore Drilling (DODRW) 8-KRegulation FD Disclosure
Filed: 26 Jul 07, 12:00am
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||
RECENT COMMITMENTS — (See Body of Report For Contract Details/Date Changes and Other Information) | ||||||||||||||||||
Ocean Rover | Two-years with Murphy in Malaysia in mid 450’s | |||||||||||||||||
Ocean Worker | 30-day extension with Pemex in mid 330’s | |||||||||||||||||
Domestic Deepwater Semisubmersibles (8) | ||||||||||||||||||
Ocean Quest | 3,500' | GOM | Contracted | Noble | two year term + option | mid 350’s | mid April 2007 | mid June 2009 | Available; actively marketing. | |||||||||
Ocean Star | 5,500' | GOM | Contracted | DODI | special survey and maintenance | — | — | late July 2007 | Resume contract with Anadarko thru early Jan. 2008; followed by one-year term extension, plusoption, with Anadarko in mid 410’s beginning in early Jan. 2008 and ending in early Jan. 2009. Available; actively marketing. | |||||||||
Ocean America | 5,500' | GOM | Contracted | ENI | assignment from Mariner | mid 420’s | mid May 2007 | mid Oct. 2007 | Resume work with Mariner mid-Oct. 2007 in mid 370’s until mid-March 2008, then mid 420’s until mid-April 2008, plusoption. Available; actively marketing. | |||||||||
Ocean Valiant | 5,500' | GOM | Contracted | Anadarko | one year term extension | mid 390’s | mid Mar. 2007 | mid Mar. 2008 | One-year term extension with Anadarko in mid 420’s beginning mid April 2008 and ending mid April 2009. Available; actively marketing. | |||||||||
Ocean Victory | 5,500' | GOM | Contracted | Murphy | two year term ext. + option | mid 320’s | early Dec. 2006 | early Dec. 2008 | One well, plus option, with Newfield in low 300’s (swap from Voyager contract in low 300’s) beginning early Dec. 2008 and ending mid Jan. 2009.Available; actively marketing. | |||||||||
Ocean Baroness | 7,000' | GOM | Contracted | DODI | special survey and maintenance | — | — | lateSept. 2007 | Current Hess contract is three year term +optionendingmidFeb. 2010. Available; actively marketing. | |||||||||
Ocean Endeavor | 10,000' | GOM | Contracted | Devon | four year term + option | low 250’s | early July 2007 | late June 2011 | Available. | |||||||||
Ocean Confidence | 7,500' | GOM | Contracted | BP | two year term | low 280’s | early Jan. 2006 | early Jan. 2008 | Four-year term with Murphy in the GOM in the low 500’s beginning January 2008 and ending January 2012. Available; actively marketing. | |||||||||
Domestic 2nd/3rd Generation Semisubmersibles (5) | ||||||||||||||||||
Ocean New Era | 1,500' | GOM | Contracted | DODI | prep and mobe for Pemex | — | — | mid Sept. 2007 | 2-1/2 year term with Pemex in mid 260’s beginningmidSept. 2007 and ending mid Feb. 2010. Available; actively marketing. | |||||||||
Ocean Voyager | 2,000' | GOM | Contracted | Newfield | three wells | low 300’s | early May 2007 | late July 2007 | Prep and mobe; followed by 2-1/2 year term with Pemex in mid 330’s beginning late Sept. 2007 and ending late Feb. 2010. Available; actively marketing. | |||||||||
Ocean Yorktown | 2,850' | GOM | Contracted | DODI | prep and mobe for Brazil | — | — | mid Mar. 2008 | Five-year term contract with Petrobras in Brazil in mid 230’s plus lump sum mobe and potential 15% bonus beginning in mid Mar. 2008 and ending in mid Mar. 2013. Available. | |||||||||
Ocean Concord | 2,200' | GOM | Contracted | Tana | term extension + option | low 270’s | early June 2007 | early Sept. 2007 | Prep and lump-sum mobe to Brazil; followed by five-year contract with Petrobras in low 230’s plus potential 15% performance bonus beginnning early Nov. 2007 and ending early Nov. 2012. Available. | |||||||||
Ocean Saratoga | 2,200' | GOM | Contracted | LLOG | six month term + option | low 120’s | late April 2007 | late Oct. 2007 | Six-month extension with LLOG in low 300’s beginning late Oct. 2007 and ending late April 2008 . Available; actively marketing. |
2
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||
Domestic Jackups (8) | ||||||||||||||||||
Ocean Crusader | 200’ MC | GOM | Contracted | Energy Partners | six month term | high 110’s | early Mar. 2007 | mid Aug. 2007 | Available; actively marketing. | |||||||||
Ocean Drake | 200’ MC | GOM | DODI | — | — | — | — | — | Available; actively marketing. | |||||||||
Ocean Champion | 250’ MS | GOM | DODI | — | — | — | — | — | Available; actively marketing. | |||||||||
Ocean Columbia | 250’ IC | GOM | Contracted | Newfield | one year term | low 120’s | early Aug. 2006 | early Aug. 2007 | Available; actively marketing. | |||||||||
Ocean Spartan | 300’ IC | GOM | Contracted | Apache | two wells | low 70’s | mid July 2007 | late Aug. 2007 | Available; actively marketing. | |||||||||
Ocean Summit | 300’ IC | GOM | Contracted | Hunt | three wells +two option wells | high 70’s | early June 2007 | mid Sept. 2007 | Available; actively marketing. | |||||||||
Ocean Titan | 350’ IC | GOM | Contracted | Apache | one well | low 80’s | early May 2007 | lateJuly 2007 | Two well extension with Apache in low 80’s beginninglateJuly and endinglateSept. 2008. Available; actively marketing. | |||||||||
Ocean Tower | 350’ IC | GOM | Contracted | Chevron | two year term extension +option | low 140’s | late April 2006 | late April 2008 | Indexed term contractwith floor in low 140’s and ceiling in low 200’s. Available; actively marketing. | |||||||||
International Semisubmersibles (17) | ||||||||||||||||||
MEXICO | ||||||||||||||||||
Ocean Ambassador | 1,100' | GOM | Contracted | PEMEX | four year term work | mid 50’s | late July 2003 | mid Dec. 2007 | Available; actively marketing. | |||||||||
Ocean Worker | 3,500' | GOM | Contracted | PEMEX | four year term work | high 60’s | mid Aug. 2003 | late July 2007 | 30-day extension with Pemex in mid 330’s beginning late July and ending late Aug. 2007; followed by mobe to GOM; survey and prep for mobe to Trinidad;followed bysix-month term with Petro-Canada in Trinidad in the low 450’s beginninglate Oct. 2007 and ending lateMay2008. Available; actively marketing. | |||||||||
NORTH SEA/MED | ||||||||||||||||||
Ocean Nomad | 1,200' | North Sea | Contracted | Talisman | 18-month extension | mid 280’s | early Feb. 2007 | early Aug. 2008 | Two-year term extension with Talisman in mid 330’s beginning early Aug. 2008 and ending early Aug. 2010. Available; actively marketing. | |||||||||
Ocean Guardian | 1,500' | North Sea | Contracted | Oilexco | two year term | mid 350’s | early June 2007 | early June 2009 | Available; actively marketing. | |||||||||
Ocean Princess | 1,500' | North Sea | Contracted | Talisman | two year term | mid 150’s | late Jan. 2006 | mid Feb. 2008 | Two-year term extension with Talisman in mid 330’s beginning mid Feb. 2008 and ending mid Feb. 2010.Available; actively marketing. | |||||||||
Ocean Vanguard | 1,500' | North Sea | Contracted | Statoil | term | mid 160’s | early April 2007 | mid April 2008 | Two year extension plusoptionwith Statoil in low 400’s beginning mid April 2008 and ending mid April 2010. Available; actively marketing. | |||||||||
Ocean Lexington | 2,200' | Egypt | Contracted | BP | 36 month term + option | mid 260’s | late Nov. 2006 | late Aug. 2009 | Available; actively marketing. |
3
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||
AUSTRALASIA | ||||||||||||||||||
Ocean Bounty | 1,500' | Australia | Contracted | Woodside | five wells | mid 100’s | early May 2007 | early Feb.2008 | One-year term with Woodside in low 350’s beginningearly Feb. 2008and endingearly Feb. 2009. Available; actively marketing. | |||||||||
Ocean Patriot | 1,500' | New Zealand | Contracted | NZOP | four wells | high 100’s | early Mar. 2007 | lateJuly 2007 | One well with NZOP in mid 370’s beginninglateJuly 2007 and endingmidAug. 2007; followed by remainder of Australian Worldwide work in New Zealand in mid 370’s beginningmidAug. and ending mid Sept. 2007; followed by remainder of New Zealand work with Santos in mid 370’s beginning mid Sept. and ending mid Dec. 2007; followed by last option well exercised with Anzon in low 350’s beginning mid Dec. 2007 and ending mid Jan. 2008; followed by remainder of Santos term plus option in mid 370’s beginning mid Feb. 2008 and ending mid Sept. 2008; followed by two-year term contract in Australia at a dayrate between 380,000 and 420,000*** with Apache, plusoption,beginning mid Sept. 2008 and ending mid Sept. 2010. Available; actively marketing. | |||||||||
Ocean Epoch | 1,640' | Australia | Contracted | Shell | term program plus option | mid 220’s | early April 2006 | mid Dec. 2007 | One year term contract with Apache in Australia at a dayrate between 330,000 and 365,000*** beginning mid Dec. 2007 and ending mid Dec. 2008; followed by 550-day term contract in Australia in low 350’s with BHPB, plusoption,beginning mid Dec. 2008 and ending mid June. 2010. Available; actively marketing. | |||||||||
Ocean General | 1,640' | Indonesia | mobing to Timor Sea | Inpex | three wells | mid 130’s | early May 2007 | early Dec. 2007 | Two additional wells with Inpex in mid 170’s beginningearly Dec. 2007 and endingmid April. 2008. Available; actively marketing. | |||||||||
Ocean Rover | 7,000' | Malaysia | Contracted | Murphy | remaining Kikeh development wells | mid 180’s | late Feb. 2007 | late April 2008 | Seven option wells of approximately 30-days each with Murphy in mid 240’sending mid Dec. 2008; followed by one well with Newfield in Malaysia in low 450’s beginning mid Dec. 2008 and ending late Jan. 2009;followed by two-year term with Murphy in Malaysia in low 450’s beginning late Jan. 2009 and ending late Jan. 2011. Available; actively marketing. | |||||||||
BRAZIL | ||||||||||||||||||
Ocean Yatzy | 3,300' | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 110’s | early Oct. 2005 | early Oct. 2009 | Available. | |||||||||
Ocean Whittington | 1,500' | Brazil | DODI— acceptance test | - | - | - | - | lateJuly 2007 | Five-year term contract with Petrobras in Brazil in mid 220’s plus lump sum mobe and potential 15% bonus beginninglateJuly 2007 and endinglateJuly 2012. Available. | |||||||||
Ocean Winner | 3,500' | Brazil | Contracted | Petrobras | 700 day extension | low 110’s | mid Mar. 2006 | mid Mar. 2010 | Available. | |||||||||
Ocean Alliance | 5,000' | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 150’s | early Sept. 2005 | early Sept. 2009 | Available. | |||||||||
International Drillships (1) | ||||||||||||||||||
Ocean Clipper | 7,500' | Brazil | Contracted | Petrobras | five year extension plus potential bonus | low 180’s | mid Dec. 2005 | mid Dec. 2010 | Available. |
4
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||
International Jackups (5) | ||||||||||||||||||
Ocean Sovereign | 300’ IC | Indonesia | Contracted | Kodeco | 18-month term +option | mid 90’s | mid Oct. 2006 | mid-April 2008 | Available; actively marketing. | |||||||||
Ocean Spur | 300’ IC | Eqypt | Contracted | NOSPCO | 180-day term | high 150’s | mid May 2007 | late Jan. 2008 | One well with Gaz de France in Egypt in low 190’s beginning late Jan. 2008 and ending late Mar. 2008. Available; actively marketing. | |||||||||
Ocean Heritage | 300’ IC | Qatar | Contracted | Maersk | one year term | high 150’s | early May 2006 | late Aug. 2007 | Two wells (approx. 150 days) plusoptionwith QPD in Qatar in mid 170’s beginning late Aug. 2007 and ending mid Jan. 2008. Available; actively marketing. | |||||||||
Ocean King | 300’ IC | Mobe to Croatia | DODI | — | — | — | — | early Aug. 2007 | Lump sum mobe followed by approximately 100 days shipyard for survey and maintenance ending mid Nov. 2007; followed by two-year bareboat charter with Crosco in high 100’s beginning early Nov. 2007 and ending mid Nov. 2009. Available; actively marketing. | |||||||||
Ocean Nugget | 300’ IC | GOM | Contracted | Pemex | term contract | high 160’s | early Oct 2006 | late Mar. 2009 | Available; actively marketing. | |||||||||
Upgrade (1) | ||||||||||||||||||
Ocean Monarch | 2,200’ | Shipyard | Upgrading | DODI | — | — | — | — | Singapore shipyard for upgrade to 10,000 ft. capable 5th Generation rig. Estimated completion, including commissioning and mobe, late fourth quarter 2008; followed by four-year term, plus mobe, plus option, with Anadarko in the GOM in the mid 420’s beginning late Dec. 2008 and ending late Dec. 2012. Available. | |||||||||
New-build Rigs Under Construction (2) | ||||||||||||||||||
Ocean Shield | 350’ IC | Shipyard | — | — | — | — | — | — | Singapore shipyard, estimated completion Q1 2008; followed by one-year term in Australia with ENI in mid 260’s beginning upon delivery in the first quarter of 2008. Available; actively marketing. | |||||||||
Ocean Scepter | 350’ IC | Shipyard | — | — | — | — | — | — | Brownsville shipyard, estimated completion Q1 2008. Available; actively marketing. |
5
Anticipated 2007 | # Days | Comments | ||||
Q3 | ||||||
Ocean Star | 28 | Completion of 5-year Special Survey and Maintenance Begun in Q2 | ||||
Ocean New Era | 65 | Completion of Mexico Prep Work Begun in Q2 and Mobe to Mexico | ||||
Ocean King | 92 | 5-year Special Survey and Maintenance Plus Mobe to, and Prep in, Croatia (cont. Q4) | ||||
Ocean Columbia | 6 | 5-year Special Survey, Tank Work, Prep for Mexico (cont. Q4) | ||||
Ocean Alliance | 11 | 5-year Special Survey and Maintenance (cont.Q4) | ||||
Ocean Concord | 21 | Brazil Contract Prep Work (cont. Q 4) | ||||
Ocean Baroness | 86 | 5-year Survey and Maintenance | ||||
Ocean Confidence | 18 | Maintenance on Thrusters | ||||
Ocean Crusader | 33 | 5-year Special Survey | ||||
Ocean Quest | 30 | 5-year Special Survey and Permanent Repairs due to Hurricane Damage (cont. Q4) | ||||
Ocean Whittington | 25 | Acceptance testing for 5-year Brazil contract | ||||
Ocean Voyager | 65 | 5-year Survey and Mexico Prep Work | ||||
Ocean Worker | 37 | Mobe to GOM and 5-year Special Survey and Maintenance | ||||
Ocean Clipper | 51 | 5-year Special Survey and Maintenance | ||||
Ocean Yorktown | 80 | Mobe to GOM, Life Extension Work, 5-year Special Survey, Prep for Brazil (cont. Q4) | ||||
648 | ||||||
Q4 | ||||||
Ocean King | 46 | Completion of 5-year Special Survey and Prep in Croatia | ||||
Ocean Alliance | 34 | Completion of 5-year Special Survey and Maintenance | ||||
Ocean Yorktown | 92 | Continuation of Life Extension Work, Special Survey, Brazil Prep. (cont. 120-days 2008) | ||||
Ocean Quest | 31 | Completion of 5-year Special Survey and Permanent Repairs Due to Hurricane Damage | ||||
Ocean Columbia | 92 | Completion of 5-year Survey plus Prep for, and Mobe to, Mexico (cont. 18 days in 2008) | ||||
Ocean Concord | 76 | Completion of Intermediate Survey and Maintenance and Mobe to Brazil | ||||
Ocean Worker | 27 | Completion of 5-year Special Survey and Maintenance and Mobe to Trinidad | ||||
Ocean Victory | 39 | 5-year Special Survey and Maintenance | ||||
Ocean Tower | 28 | 5-year Special Survey and Maintenance | ||||
Ocean Vanguard | 20 | Intermediate Survey and Maintenance | ||||
Ocean Ambassador | 21 | Mobe to GOM, Start of 5-year Special Survey and Maintenance (cont. 24 days in 2008) | ||||
506 | ||||||
Total Anticipated Remaining 2007 | 1,154 | |||||
Total 2007 Estimate | 1,684 |