Diamond Offshore Drilling (DODRW) 8-KRegulation FD Disclosure
Filed: 24 Apr 08, 12:00am
1 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||
April 24, 2008 |
RECENT COMMITMENTS — (See Body of Report For Contract Details/Date Changes and Other Information) | ||||||||||||||||||
Ocean Guardian | Two-year extension in U.K. North Sea | |||||||||||||||||
Ocean Shield | LOI for five-month term in Malaysia | |||||||||||||||||
Ocean Summit | One-well extension plus option | |||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||
Domestic Deepwater Semisubmersibles (8) | ||||||||||||||||||
Ocean Quest | 3,500’ | GOM | Contracted | Noble | two year term + option | upper 350’s | mid June 2007 | mid June 2009 | Available; actively marketing. | |||||||||
Ocean Star | 5,500’ | GOM | Contracted | Anadarko | term extension | upper 410’s | late Nov. 2007 | late Nov. 2008 | Available; actively marketing. | |||||||||
Ocean America | 5,500’ | GOM | Contracted | Mariner | term | upper 460’s | mid March 2008 | early July 2009 | Available, actively marketing. | |||||||||
Ocean Valiant | 5,500’ | GOM | Contracted | Anadarko | one year term extension | upper 420’s | mid March 2008 | late June 2009 | One-year term extension interrupted forspecial survey and maintenance expected to begin mid July and end mid Oct. 2008. Available; actively marketing. | |||||||||
Ocean Victory | 5,500’ | GOM | Contracted | Murphy | completion Murphy contract | upper 330’s | late July 2007 | mid July 2008 | Callon and Newfield have swapped slots. Next up is now two wells with Callon in low 500’s beginning mid July 2008 and ending mid Jan. 2009; followed by one well with Newfield in low 300’s (swap from old Voyager contract in low 300’s) beginning mid Jan. 2009 and ending mid Mar. 2009; followed by one well extension with Newfield plus option in low 500’s beginning mid Mar. 2009 and ending late April 2009. Available; actively marketing. | |||||||||
Ocean Baroness | 7,000’ | GOM | Contracted | Hess | three year term extension +option | mid 360’s | late Nov. 2007 | late Nov. 2009 | Available; actively marketing. | |||||||||
Ocean Confidence | 7,500’ | GOM | Contracted | Murphy | four year term +option | low 500’s | late Feb. 2008 | mid March 2012 | Thruster maintenance early Oct. to mid Oct. 2008. Available. | |||||||||
Ocean Endeavor | 10,000’ | GOM | Contracted | Devon | four year term +option | mid 260’s | early July 2007 | late June 2011 | Available. | |||||||||
Domestic 2nd/3rd Generation Semisubmersibles (3) | ||||||||||||||||||
Ocean Yorktown | 2,850’ | GOM | Contracted | DODI | prep, mobe and acceptance test for Brazil | — | — | late July 2008 | Five-year term contract with Petrobras in Brazil in mid 230’s plus lump sum mobe and potential 15% bonus beginning inlate July 2008 and ending inlate July 2013. Available. | |||||||||
Ocean Ambassador | 1,100’ | GOM | Contracted | Apache | one well | mid 270’s | early April 2008 | late May 2008 | 5-year survey and maintenance late May to mid Aug. 2008. Available; actively marketing. | |||||||||
Ocean Saratoga | 2,200’ | GOM | Contracted | LLOG | six month term +option | low 300’s | late Oct. 2007 | lateJune 2008 | Available; actively marketing. |
2 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||
April 24, 2008 |
Dayrate | Est. End | |||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | (000s) | Start Date | Date | Future Contracts and Other Information* | |||||||||
Domestic Jackups (7) | ||||||||||||||||||
Ocean Crusader | 200’ MC | GOM | Contracted | Apache | three wells + option | low 60’s | early March 2008 | late May 2008 | Available; actively marketing. | |||||||||
Ocean Drake | 200’ MC | GOM | Contracted | Fairways Offshore | one well | low 60’s | late Feb. 2008 | mid May 2008 | One well with Walter in low 60’s beginningmid May and endinglate June 2008; followed by 5-year survey and maintenance beginninglate June and endingmid August 2008. Available; actively marketing. | |||||||||
Ocean Champion | 250’ MS | GOM | Contracted | Bois d’Arc | 90-day term + option | high 50’s | late April 2008 | early July 2008 | Available; actively marketing. | |||||||||
Ocean Spartan | 300’ IC | GOM | Contracted | Apache | one well | low 80’s | mid April 2008 | late April 2008 | Four wells plus option with Samson in mid 80’s beginninglate April and endinglate July 2008. Available; actively marketing. | |||||||||
Ocean Summit | 300’ IC | GOM | Contracted | Energy Partners | one well extension + option | mid 80’s | late April 2008 | late May 2008 | Available; actively marketing. | |||||||||
Ocean Titan | 350’ IC | GOM | Contracted | Apache | two wells | mid 80’s | mid Feb. 2008 | mid May 2008 | Three wells plusoption with Apache in low 100’s, mid 100’s and low 110’s, respectively, beginning mid May and ending early Oct. 2008. Available; actively marketing. | |||||||||
Ocean Tower | 350’ IC | GOM | Contracted | Chevron | indexed term contract | low 140’s | early Dec. 2007 | late April 2008 | 90-day extension plusoptionwith Chevron in mid 100’s beginning late April and ending late July, 2008. Available; actively marketing. | |||||||||
International Semisubmersibles (18) | ||||||||||||||||||
MEXICO | ||||||||||||||||||
Ocean New Era | 1,500’ | Mexico | Contracted | PEMEX | 2 1/2-year term | mid 260’s | late Oct. 2007 | mid Feb. 2010 | Available. | |||||||||
Ocean Voyager | 3,000’ | Mexico | Contracted | PEMEX | 2-1/2 year term | mid 330’s | early Nov. 2007 | late Feb. 2010 | Available. | |||||||||
NORTH SEA/MED | ||||||||||||||||||
Ocean Nomad | 1,200’ | North Sea | Contracted | Talisman | 18-month extension | mid 280’s | early Feb. 2007 | late Sept. 2008 | Survey and maintenance beginning late July 2008 and ending late Sept. 2008; followed by resumption of Talisman extension ending late Sept. 2008; followed by two-year term extension with Talisman in mid 330’s beginning late Sept. 2008 and ending late Sept. 2010. Available; actively marketing. | |||||||||
Ocean Guardian | 1,500’ | North Sea | Contracted | Oilexco | two year term | low 350’s | early June 2007 | mid July 2009 | Intermediate survey and maintenance late June to early Aug. 2008. Two-year extension with Oilexco in mid 380’s beginning mid July 2009 and ending mid July 2011. Available; actively marketing. | |||||||||
Ocean Princess | 1,500’ | North Sea | Contracted | Talisman | two year term extension | upper 330’s | mid Feb. 2008 | mid April 2010 | 5-year survey and maintenance beginning late July and ending late Sept. 2008. Available; actively marketing. | |||||||||
Ocean Vanguard | 1,500’ | North Sea | Contracted | Statoil | resume contract | low 160’s | mid Jan. 2008 | late April 2008 | Two year extension plusoptionwith Statoil in low 400’s beginning late April 2008 and endingmid April2010. Available; actively marketing. | |||||||||
Ocean Lexington | 2,200’ | Egypt | Contracted | BP | 36 month term + option | mid 260’s | late Nov. 2006 | mid Aug. 2009 | Available; actively marketing. |
3 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||
April 24, 2008 |
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||||
AUSTRALASIA | ||||||||||||||||||||
Ocean Bounty | 1,500’ | Australia | Contracted | Chevron | sublet from Woodside | low 350’s | early Feb. 2008 | early Aug. 2008 | Special Survey beginning early Aug. 2008 and ending mid Sept. 2008; followed by remainder of one-year term with Woodside in low 350’s beginning mid Sept. 2008 and ending mid March 2009; followed by 240-day re-engine and upgrade ending mid Nov. 2009; followed by two year extension from Woodside in Australia in mid 420’s beginning mid Nov. 2009 and ending mid Nov. 2011. Available; actively marketing. | |||||||||||
Ocean Patriot | 1,500’ | Australia | Contracted | Anzon | one well | low 350’s | early March 2008 | late April 2008 | Remainder of Santos term plus option in high 370’s beginninglate April 2008 and endingearly Dec. 2008; followed by two-year term contract in Australia at a dayrate between 380,000 and 420,000*** with Apache, plus option, beginningearly Dec. 2008 and endingearly Dec. 2010. Available; actively marketing. | |||||||||||
Ocean Epoch | 1,640’ | Australia | Contracted | Apache | one-year term | low 350’s | early March 2008 | early March 2009 | 550-day term contract in Australia in low 350’s with BHPB, plus option, beginning early March 2009 and ending early Sept. 2010. Available; actively marketing. | |||||||||||
Ocean General | 2,400 | Indonesia | Contracted | Inpex | one well | mid 170’s | late Feb. 2008 | lateMay 2008 | 5-year survey and maintenance beginning late May and ending mid July 2008; followed by approximately 730 day’s work plus option in Vietnam with PVEP in low 280’s beginningmid July 2008 and endingmid July 2010. Available; actively marketing. | |||||||||||
Ocean Rover | 7,000’ | Malaysia | Contracted | Murphy | balance of previously declared option wells | high 240’s | late Feb. 2008 | late Dec. 2008 | Single deepwater well in low 350’s beginninglate June and ending late July; followed byUWILD survey and maintenance beginning late July 2008 and ending early Sept.; followed by balance of previously declared option wells in high 240’s beginning early Sept. and ending late Dec. 2008; followed by one well with Newfield in Malaysia in low 450’s beginning late Dec. 2008 and ending early Feb. 2009; followed by two-year term with Murphy in Malaysia in low 450’s beginning early Feb. 2009 and ending early Feb. 2011. Available; actively marketing. |
4 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||
April 24, 2008 |
Est. End | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate (000s) | Start Date | Date | Future Contracts and Other Information* | |||||||||
BRAZIL/TRINIDAD | ||||||||||||||||||
Ocean Whittington | 1,500’ | Brazil | Contracted | Petrobras | five year term plus potential bonus | mid 220’s | late Aug. 2007 | late Aug. 2012 | Resume and complete contract upgrade work beginning early Oct. 2008 and ending late Nov. 2008; followed by resumption of five year term in mid 220’s plus potential 15% performance bonus. Available. | |||||||||
Ocean Concord | 2,200’ | Brazil | Contracted | Petrobras | five year term plus potential bonus | low 230’s | mid Jan. 2008 | mid Jan. 2013 | Available. | |||||||||
Ocean Yatzy | 3,300’ | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 110’s | early Oct. 2005 | early Oct. 2009 | Five-year term extension in mid 240’s plus potential 10% performance bonus beginning early Oct. 2009 and ending early Oct. 2014. Available. | |||||||||
Ocean Winner | 3,500’ | Brazil | Contracted | Petrobras | four year extension plus potential bonus | low 110’s | mid Mar. 2006 | mid Mar. 2010 | Five-year term extension in low 270’s plus potential 10% performance bonus beginning mid Mar. 2010 and ending mid Mar. 2015. Available. | |||||||||
Ocean Worker | 3,500’ | Trinidad | Contracted | Petro-Canada | six-month term | low 450’s | mid Nov. 2007 | early June 2008 | Lump sum mobe to Brazil plus subsequent acceptance test beginning early June 2008 and ending mid Sept. 2008; followed by six-year term contract with Petrobras in low 270’s plus potential 10% performance bonus beginning mid Sept. 2008 and ending mid Sept. 2014. Available. | |||||||||
Ocean Alliance | 5,000’ | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 150’s | mid Jan. 2008 | early Sept. 2009 | Six-year term extension in low 340’s plus potential 15% performance bonus beginning early Sept. 2009 and ending early Sept. 2015. Available. | |||||||||
International Drillships (1) | ||||||||||||||||||
Ocean Clipper | 7,500’ | Brazil | Contracted | DODI | survey and maintenance | — | — | late April 2008 | Resume five year extension in low 180’s plus potential 5% performance bonus ending mid Dec. 2010. Available. | |||||||||
International Jackups (6) | ||||||||||||||||||
Ocean Columbia | 250’ IC | Mexico | Contracted | Pemex | 1-1/2 year term | mid 120’s | late Jan. 2008 | mid June 2009 | Available; actively marketing. | |||||||||
Ocean Nugget | 300’ IC | Mexico | Contracted | Pemex | term contract | upper 160’s | early Oct 2006 | late Mar. 2009 | Available; actively marketing. | |||||||||
Ocean King | 300’ IC | Croatia | Contracted | CROSCO | two year bareboat charter | upper 100’s | mid Nov. 2007 | early Nov. 2009 | Two-year bareboat charter with Crosco in high 100’s, beginning mid Nov. 2007 and ending early Nov. 2009. Available; actively marketing. | |||||||||
Ocean Sovereign | 300’ IC | Indonesia | Contracted | Kodeco | 18-month term + option | mid 90’s | mid Oct. 2006 | mid-June 2008 | Intermediate survey early July to late July 2008; followed by two-year term extension with Kodeco in mid 140’s beginninglate July 2008 and endingmid Jan. 2010. Available; actively marketing. | |||||||||
Ocean Heritage | 300’ IC | UAE | - | DODI | hot stacked | — | — | — | Available; actively marketing. | |||||||||
Ocean Spur | 300’ IC | Egypt | Contracted | Gaz de France | one well | low 190’s | late March 2008 | late May 2008 | One well with British Gas in Egypt in mid 130’s beginning late May and ending in late July 2008. Available; actively marketing. |
5 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||
April 24, 2008 |
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate (000s) | Start Date | Est. End Date | Future Contracts and Other Information* | |||||||||
Upgrade (1) | ||||||||||||||||||
Ocean Monarch | 2,200’ | Shipyard | — | DODI | — | — | — | — | Singapore shipyard for upgrade to 10,000 ft. capable 5th Generation rig. Estimated completion, including commissioning and commencement of mobe to GOM, late fourth quarter 2008; followed by completion of mobe to GOM and rig prep ending late Feb. 2009; followed by four-year term, plus option, with Anadarko in the GOM in the upper 420’s beginning late Feb. 2009 and ending late Feb. 2013. Available. | |||||||||
Newbuild Rigs Under Construction (2) | ||||||||||||||||||
Ocean Shield | 350’ IC | Commissioning | — | DODI | — | — | — | — | Commissioning, followed by mobe to Malaysia ending late May 2008; followed by LOI for five-month term in Malaysia in mid 170’s beginning late May and ending late Oct. 2008; followed by mobe to Australia for one-year term with ENI in mid 260’s beginning mid Nov. 2008 and ending late Oct. 2009. Available; actively marketing. | |||||||||
Ocean Scepter | 350’ IC | Shipyard | — | — | — | — | — | — | Brownsville shipyard completion, commissioning ending late May 2008; followed by mobe to destination to be determined. Available; actively marketing. |
6 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||
April 24, 2008 |
# Days | |||||||||||||||||||||||
Rig | Q2 | Q3 | Q4 | Total | Comments | ||||||||||||||||||
Shipyard Time | |||||||||||||||||||||||
Yorktown | 91 | 25 | 116 | Complete life extension/5-yr. survey, Brazil mobe, accpt. Test (46 over prev. guidance) | |||||||||||||||||||
Bounty | 41 | 41 | 5-year survey and maintenance | ||||||||||||||||||||
Nomad | 52 | 52 | 5-year survey and maintenance | ||||||||||||||||||||
Drake | 22 | 29 | 51 | 5-year survey and maintenance | |||||||||||||||||||
Rover | 47 | 47 | 5-year survey and maintenance | ||||||||||||||||||||
General | 38 | 14 | 52 | 5-year survey and maintenance | |||||||||||||||||||
Princess | 58 | 58 | 5-year survey and maintenance | ||||||||||||||||||||
Ambassador | 31 | 50 | 81 | 5-year survey and maintenance | |||||||||||||||||||
Guardian | 6 | 37 | 43 | North Sea intermediate survey and maintenance | |||||||||||||||||||
Valiant | 78 | 18 | 96 | 5-year survey/replace derrick and other maintenance | |||||||||||||||||||
188 | 431 | 18 | 637 | ||||||||||||||||||||
Other Downtime | |||||||||||||||||||||||
Clipper | 25 | 25 | 12 complete survey/subsequent 13 equipment repairs (16 over previous guidance) | ||||||||||||||||||||
Whittington | 51 | 51 | Complete contract upgrade | ||||||||||||||||||||
Sovereign | 19 | 19 | Intermediate survey and install new top drive system | ||||||||||||||||||||
Worker | 30 | 74 | 104 | Mobe to Brazil, prep for contract, contract acceptance testing | |||||||||||||||||||
Confidence | 18 | 18 | Change out thruster (4 over previous guidance) | ||||||||||||||||||||
55 | 93 | 69 | 217 | ||||||||||||||||||||
Remaining Total 2008 Non New-build/Upgrade | 243 | 524 | 87 | 854 | |||||||||||||||||||
New-build/Upgrade Downtime | Q2 | Q3 | Q4 | Total | |||||||||||||||||||
Shield | 56 | 56 | Complete construction, commissioning, mobe to Malaysia | ||||||||||||||||||||
Shield | 22 | 22 | Mobe to Australia | ||||||||||||||||||||
Scepter | 61 | 61 | Complete construction, commissioning | ||||||||||||||||||||
Scepter | ?? | ?? | Mobe to ?? | ||||||||||||||||||||
Monarch | 91 | 92 | 92 | 275 | Complete upgrade, commissioning, begin mobe to U.S. GOM | ||||||||||||||||||
7 | DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF | |||