Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | ($000s) | Start Date | Est. End Date | ||||||||||
Domestic Deepwater Semisubmersibles (8) | ||||||||||||||||||
Ocean Quest | 3,500’ | GOM | Current Contract | Noble | two-year term + unpricedoption | upper 350’s | mid June 2007 | mid June 2009 | ||||||||||
GOM/Brazil | Prep, mobe & acceptance test for OGX | OGX | 0 | mid June 2009 | early Oct. 2009 | |||||||||||||
Brazil | Future Contract | OGX | two-year term + unpricedoption | low 420’s | early Oct. 2009 | early Oct. 2011 | ||||||||||||
Ocean Star | 5,500’ | GOM | Current Contract | Anadarko | term extension | upper 410’s | early Nov. 2007 | midDec. 2008 | ||||||||||
Ocean America | 5,500’ | GOM | Current Contract | Mariner | term | mid 460’s | late Oct. 2008 | mid July 2009 | ||||||||||
GOM | Special Survey & Maintenance | DODI | 0 | midJan. 2009 | early April2009 | |||||||||||||
GOM | Future Contract | Mariner | 1-year term; convertible to 6- month term (ending Jan. 2010) in low 550’s w/notice by 1- Feb.-09 | low530’s | mid July 2009 | mid July 2010 | ||||||||||||
Ocean Valiant | 5,500’ | GOM | Special Survey & Maintenance | DODI | 0 | early Aug. 2008 | late Nov. 2008 resume contract | |||||||||||
GOM | Current Contract | Anadarko | resume one-year term extension | upper 420’s | late Nov. 2008 | mid July 2009 | ||||||||||||
Mobe | Lump sum mobe | DODI | mid July 2009 | mid Sept. 2009 | ||||||||||||||
Angola | Future Contract | Total | two-year term +priced options | low 620’s | mid Sept. 2009 | mid Sept. 2011 | ||||||||||||
Ocean Victory | 5,500’ | GOM | Current Contract | Callon | two wells | low 500’s | mid Aug. 2008 | lateMarch 2009 | ||||||||||
GOM | Future Contract (swap from oldVoyagercontract in low 300’s) | Newfield | one well | low 300’s | lateMarch 2009 | early May 2009 | ||||||||||||
GOM | Future Contract | Newfield | one well extension | low 500’s | early May 2009 | mid June 2009 | ||||||||||||
GOM | Future Contract | ATP | one-year term, minimum | low 540’s | mid June 2009 | mid June 2010 | ||||||||||||
Ocean Baroness | 7,000’ | GOM | Current Contract | Hess | term extension +unpricedoption | mid 360’s | late Nov. 2007 | mid April 2010 | ||||||||||
Ocean Confidence | 10,000’ | GOM | Current Contract | Murphy | four-year term + unpricedoption | low 500’s | late Feb. 2008 | late March 2012 | ||||||||||
Ocean Endeavor | 10,000’ | GOM | Current Contract | Devon | four-year term + unpriced option | mid 260’s | early July 2007 | late June 2011 | ||||||||||
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | ($000s) | Start Date | Est. End Date | ||||||||||
Domestic 2nd and 3rd Generation Semisubmersibles (2) | ||||||||||||||||||
Ocean Ambassador | 1,100’ | GOM | Special Survey & Maintenance (storm delayed) | DODI | 0 | early Aug. 2008 | late Nov. 2008 | |||||||||||
GOM | Future Contract | Taylor | seven-month term | mid 280’s | late Nov. 2008 | early June 2009 | ||||||||||||
GOM/Brazil | Prep, mobe & acceptance test for OGX | OGX | 0 | early June 2009 | mid Sept. 2009 | |||||||||||||
Brazil | Future Contract | OGX | three-year term + unpriced option | low 260’s | mid Sept. 2009 | mid Sept. 2012 | ||||||||||||
Ocean Saratoga | 2,200’ | GOM | Current Contract | Deep Gulf | one well | mid 280’s | late Oct. 2008 | early Dec. 2008 | ||||||||||
GOM | Future Contract | Walter | four wells | mid 280’s | early Dec. 2008 | early April2009 | ||||||||||||
GOM | Future Contract | Taylor | 16-month term +option | mid 280’s | early April2009 | mid July 2010 | ||||||||||||
Domestic Jack-ups (7) | ||||||||||||||||||
Ocean Crusader | 200’ MC | GOM | Current Contract | Walter | two wells | mid 70’s | mid Oct. 2008 | late Dec. 2008 | ||||||||||
Ocean Drake | 200’ MC | GOM | Current Contract | Tarpon | one well | mid 60’s | late Oct. 2008 | mid Dec. 2008 | ||||||||||
GOM | Future Contract | Tarpon | two wells | mid 70’s | mid Dec. 2008 | mid Feb. 2009 | ||||||||||||
Ocean Champion | 250’ MS | GOM | Current Contract | Stone | one well | low 70’s | early Sept. 2008 | mid Nov. 2008 | ||||||||||
GOM | Future Contract | Stone | six months + unpricedoption | low 70’s | late Oct. 2008 | late April 2009 | ||||||||||||
Ocean Spartan | 300’ IC | GOM | Current Contract | Samson | two-well extension, part 1 | low 100’s | early Nov. 2008 | mid Dec. 2008 | ||||||||||
GOM | Future Contract | Samson | two-well extension, part 2 | low 120’s | mid Dec. 2008 | early Feb. 2009 | ||||||||||||
Ocean Summit | 300’ IC | GOM | Current Contract | W&T | one well | low 140’s | late Oct. 2008 | mid Nov.2008 | ||||||||||
GOM | Resume Previous EP Contract | Energy Partners | five-wells + unpriced option | low 100’s | mid Nov.2008 | lateDec. 2008 | ||||||||||||
Ocean Titan | 350’ IC | GOM | Current Contract | Apache | second of three wells | high 100’s | late Sept. 2008 | midNov. 2008 | ||||||||||
GOM | Future Contract | Apache | third of three wells | low 110’s | midNov. 2008 | lateDec. 2008 | ||||||||||||
GOM | Future Contract | Apache | four-month extension + unpricedoption | low 130’s | lateDec. 2008 | lateApril 2009 | ||||||||||||
Ocean Tower | 350’ IC | GOM | Hurricane Ike Repairs | DODI | mid Oct. 2008 | early Oct. 2009 | ||||||||||||
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | ($000s) | Start Date | Est. End Date | ||||||||||
International Semisubmersibles (19) | ||||||||||||||||||
MEXICO | ||||||||||||||||||
Ocean New Era | 1,500’ | GOM | Current Contract | PEMEX | 2 1/2 year term | mid 260’s | late Oct. 2007 | mid Feb. 2010 | ||||||||||
Ocean Voyager | 3,000’ | GOM | Current Contract | PEMEX | 2 1/2 year term | mid 330’s | early Nov. 2007 | late Feb. 2010 | ||||||||||
NORTH SEA/MEDITERRANEAN | | | | | | | | |||||||||||
Ocean Nomad | 1,200’ | North Sea | Current Contract | Talisman | resume two-year term extension | mid 330’s | late Oct. 2008 | late Sept. 2010 | ||||||||||
Ocean Guardian | 1,500’ | North Sea | Current Contract | Oilexco | remainder two-year term | low 350’s | early Sept. 2008 | mid July 2009 | ||||||||||
North Sea | Future Contract | Oilexco | two-year term extension | mid 380’s | mid July. 2009 | early Sept. 2011 | ||||||||||||
Ocean Princess | 1,500’ | North Sea | Contract interrupted for Special Survey & Maintenance | DODI | 0 | late Oct. 2008 | mid Dec. 2008 resume contract | |||||||||||
North Sea | Current Contract | Talisman | resume two-year term extension | upper 330’s | mid Dec. 2008 | mid April 2010 | ||||||||||||
Ocean Vanguard | 1,500’ | North Sea | Current Contract | Statoil | two-year term extension + unpricedoption | mid 400’s | late April 2008 | mid April 2010 | ||||||||||
Ocean Lexington | 2,200’ | Egypt | Current Contract | BP | 36-month term | mid 260’s | late Nov. 2006 | mid Aug.2009 | ||||||||||
Egypt/Brazil | Prep, mobe & acceptance test for OGX | OGX | 0 | mid Aug. 2009 | late Jan. 2010 | |||||||||||||
Brazil | Future Contract | OGX | three-year term + unpricedoption | mid 330’s | late Jan. 2010 | late Jan. 2013 | ||||||||||||
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | ($000s) | Start Date | Est. End Date | ||||||||||
AUSTRALASIA | ||||||||||||||||||
Ocean Bounty | 1,500’ | Australia | Current Contract | Woodside | continue one-year term | low 350’s | early Sept. 2008 | late March 2009 | ||||||||||
Australia | Re-engine and upgrade | DODI | 0 | late March 2009 | to be determined followed by two-year term | |||||||||||||
Australia | Future Contract | Woodside | two-year term + unpricedoption | mid 420’s | to be determined | to be determined | ||||||||||||
Ocean Patriot | 1,500’ | Australia | Current Contract | Apache | one-year term + unpricedoption | upper 370’s | mid May 2008 | late Dec. 2008 | ||||||||||
Australia | Future Contract | Apache | two-year term + unpricedoption | between 380-420 | late Dec. 2008 | late Dec. 2010 | ||||||||||||
Ocean Epoch | 1,640’ | Australia | Current Contract | Apache | one-year term | mid 350’s | early March 2008 | early March 2009 | ||||||||||
Australia | Future Contract | BHPB | 550-day term + unpricedoptions | low 350’s | early March 2009 | early Sept. 2010 | ||||||||||||
Ocean General | 2,400’ | Vietnam | Future Contract | PVEP | Approx. two-year term + unpricedoptions | low 280’s | mid Oct. 2008 | lateOct. 2010 | ||||||||||
Ocean Rover | 7,000’ | Malaysia | Current Contract | Resume Murphy contract | balance previously declared option wells | high 240’s | mid Oct. 2008 | midJan. 2009 | ||||||||||
Malaysia | Future Contract | Newfield | one well | low 450’s | midJan. 2009 | late Feb. 2009 | ||||||||||||
Malaysia | Future Contract | Murphy | two-year term extension | low 450’s | late Feb. 2009 | late Feb. 2011 | ||||||||||||
Dayrate | ||||||||||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | ($000s) | Start Date | Est. End Date | ||||||||||
BRAZIL | ||||||||||||||||||
Ocean Whittington | 1,500’ | Brazil | Contract interrupted to resume and complete contract upgrade work | DODI | 0 | mid Oct. 2008 | mid Dec. 2008 resume contract | |||||||||||
Brazil | Current Contract | Petrobras | resume five-year term plus potential 15% bonus | mid 220’s | midDec. 2008 | late Aug. 2012 | ||||||||||||
Ocean Concord | 2,200’ | Brazil | Current Contract | Petrobras | five-year term plus potential 15% bonus | low 230’s | mid Jan. 2008 | mid Jan. 2013 | ||||||||||
Ocean Yorktown | 2,850’ | Brazil | Current Contract | Petrobras | five-year term plus potential 15% bonus | mid 230’s | mid Aug. 2008 | mid Aug. 2013 | ||||||||||
Ocean Yatzy | 3,300’ | Brazil | Current Contract | Petrobras | four-year term extension plus potential 17% bonus | mid 110’s | early Oct. 2005 | early Oct. 2009 | ||||||||||
Brazil | Future Contract | Petrobras | five-year term plus potential 10% bonus | mid 240’s | early Oct. 2009 | early Oct. 2014 | ||||||||||||
Ocean Winner | 3,500’ | Brazil | Current Contract | Petrobras | four-year term extension plus potential 5% bonus | low 110’s | mid March 2006 | mid March 2010 | ||||||||||
Brazil | Future Contract | Petrobras | five-year term extension plus potential 10% bonus | low 270’s | mid March 2010 | mid March 2015 | ||||||||||||
Ocean Worker | 3,500’ | Brazil | Current | DODI | prep., plus acceptance testing | 0 | late July 2008 | late Dec. 2008 | ||||||||||
Brazil | Future Contract | Petrobras | six-year term plus potential 10% bonus | low 270’s | late Dec. 2008 | late Dec. 2014 | ||||||||||||
Ocean Alliance | 5,000’ | Brazil | Current Contract | Petrobras | one-well extension retroactive to late March 2008 | mid 520’s | late March 2008 | lateNov. 2008 resume contract | ||||||||||
Brazil | Resume Contract | Petrobras | resume four-year extension plus 20% potential bonus | mid 150’s | lateNov. 2008 | late Nov. 2009 | ||||||||||||
Brazil | Future Contract | Petrobras | six-year term extension plus potential 15% bonus | low 340’s | late Nov. 2009 | late Nov. 2015 | ||||||||||||
International Drillship (1) | ||||||||||||||||||
Ocean Clipper | 7,000’ | Brazil | Current Contract | Petrobras | five-year extension plus potential 5% bonus | low 180’s | mid Dec. 2005 | mid Dec. 2010 | ||||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||
International Jack-ups (8) | ||||||||||||||||
Ocean Columbia | 250’ IC | Mexico | Current Contract | Pemex | 1 1/2-year term | mid 120’s | late Jan. 2008 | mid June 2009 | ||||||||
Ocean Nugget | 300’ IC | Mexico | Current Contract | Pemex | term contract | upper 160’s | early Oct. 2006 | late March 2009 | ||||||||
Ocean King | 300’ IC | Croatia | Current Contract | CROSCO | two-year bareboat charter | upper 100’s | mid Nov. 2007 | early Nov. 2009 | ||||||||
Ocean Sovereign | 300’ IC | Indonesia | Current Contract | Kodeco | extension up to survey | upper 130’s | early Aug. 2008 | late Dec. 2008 | ||||||||
Singapore | Intermediate Survey & upgrade | DODI | 0 | late Dec. 2008 | early March 2009 | |||||||||||
Indonesia | Future Contract | Kodeco | 15-month extension + unpriced option | mid 140’s | earlyMarch2009 | late April 2010 | ||||||||||
Ocean Heritage | 300’ IC | Gulf of Suez | Current Contract | IPR | seven-month term | mid 110’s | mid July 2008 | late Dec. 2008 | ||||||||
Ocean Spur | 300’ IC | Egypt | Current Contract | WEPCO | one-year term | low 140’s | mid Aug. 2008 | late Aug. 2009 | ||||||||
Ocean Shield | 350’ IC | Malaysia | Current Contract | Newfield | six-month term + two wells | mid 170’s | late May 2008 | mid Dec. 2008 | ||||||||
Malaysia | Future Contract | Newfield | demobe to Singapore, then mobe to Australia followed by term | 0 | mid Dec. 2008 | early Jan. 2009 | ||||||||||
Australia | Future Contract | ENI | term | mid 260’s | early Jan. 2009 | mid Dec. 2009 | ||||||||||
Ocean Scepter | 350’ IC | Argentina | Current Contract | Enap Sipetrol/YPF | 300-day term contract + unpriced option | high 190’s | late Sept. 2008 | late July 2009 | ||||||||
Rig Name | WD | Location | Status | Operator | Current Term | Dayrate ($000s) | Start Date | Est. End Date | ||||||||
Upgrade (1) | ||||||||||||||||
Ocean Monarch | 10,000 | Singapore | Current | DODI | commission, wait on dry tow vessel | 0 | late Sept. 2008 | mid Dec. 2008 | ||||||||
mobe GOM | Future | DODI | mobe to GOM and prep for contract | 0 | mid Dec. 2008 | mid March 2009 | ||||||||||
GOM | Future Contract | Anadarko | four-year term + unpricedoption | high 420’s | mid March 2009 | mid March 2013 | ||||||||||
NOTES: | Generally, rig utilization rates approach 95-98% during contracted periods; however, utilization rates can be adversely impacted by additional downtime due to unscheduled repairs and maintenance, weather conditions and other factors. An LOI is subject to customary conditions, including the execution of a definitive agreement and as such may not result in a binding contract. Options are un-priced and any extension of contract is subject to mutually agreeable terms & conditions unless otherwise indicated. Mobe revenues (if any) and mobe expenses are deferred, and generally are amortized over the life of the contract. GOM = Gulf of Mexico. |
Actual Oct. 1 - 31 Down Days (Total thru Q3 = 1,111) | # Days | |||||||||
Rig | Q4 Act. TD | EST. Q4 Total | Comments | |||||||
Shipyard Time | ||||||||||
Princess | 0 | 59 | 5-year survey and maintenance | |||||||
Ambassador | 31 | 57 | 5-year survey and maintenance | |||||||
Valiant | 31 | 61 | 5-year survey/replace derrick and other maint. | |||||||
Nomad | 31 | 43 | 5-year survey and maintenance | |||||||
Drake | 31 | 31 | 5-year survey and maintenance | |||||||
Rover | 16 | 16 | 5-year survey and maintenance | |||||||
140 | 267 | |||||||||
Other Downtime | ||||||||||
Worker | 31 | 87 | Prep for contract, accpt. test | |||||||
Tower | 31 | 76 | Equipment repair (Hurricane Ike damage) | |||||||
Whittington | 19 | 60 | Complete contract upgrade | |||||||
Sovereign | 0 | 9 | Intermediate survey, install new crane & top drive | |||||||
Shield | 0 | 30 | Mobe to Australia | |||||||
81 | 262 | |||||||||
Remaining 2008 Non-New-build/Upgrade | 221 | 529 | ||||||||
New-build/Upgrade Downtime | Q4 | Total | ||||||||
Monarch | 31 | 92 | Commission, mobe to U.S. GOM | |||||||
5-YEAR SURVEYS | DAYS | COMMENTS | ||||
America | 81 | |||||
Champion | 61 | |||||
Concord | 51 | |||||
Titan | 45 | |||||
Yatzy | 42 | |||||
INTERMEDIATE SURVEYS | ||||||
Summit | 16 | |||||
Columbia | 15 | |||||
Nugget | 13 | |||||
Heritage | 10 | |||||
OTHER DOWNTIME | ||||||
Bounty | ??? | Approx. 1 year re-engine and water depth upgrade — work start time to be determined, may extend into 2010 | ||||
Tower | 274 | Hurricane repair | ||||
Lexington | 161 | Prep, mobe & acceptance test | ||||
Quest | 135 | Prep, mobe & acceptance test | ||||
Ambassador | 110 | Prep, mobe & acceptance test | ||||
Monarch | 75 | Complete mobe to GOM and rig prep. | ||||
Valiant | 60 | Mobe | ||||
Sovereign | 33 | Completion of maintenance and upgrade begun in 2008 | ||||
Confidence | 18 | Thruster changeout | ||||