Date of report (Date of earliest event reported): August 29, 2019
ARGAN, INC.
(Exact Name of Registrant as Specified in its Charter)
Delaware |
| 001-31756 |
| 13-1947195 |
(State or Other Jurisdiction |
| (Commission |
| (IRS Employer |
One Church Street, Suite 201, Rockville, MD |
| 20850 |
(Address of Principal Executive Offices) |
| (Zip Code) |
Registrant’s telephone number, including area code: (301) 315-0027
Not Applicable
(Former Name or Former Address, if Changed Since Last Report)
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the Registrant under any of the following provisions:
o Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
o Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
o Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
o Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
Indicate by check mark whether the Registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).
Emerging growth company o
If an emerging growth company, indicate by check mark if the Registrant has elected not to use the extended transition period
for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. o
Title of Each Class: |
| Trading Symbol(s): |
| Name of each exchange on |
Common Stock, $0.15 par value |
| AGX |
| NYSE |
Item 8.01. Other Events.
On August 29, 2019, Argan, Inc. (“Argan”) issued a press release announcing that its wholly owned subsidiary, Gemma Power Systems (“Gemma”), received Notice to Proceed with engineering, procurement and construction activities under a contract for a 1,875 MW natural gas-fired power plant in Guernsey County, Ohio. Construction of this state-of-the-art combined cycle facility is scheduled to begin immediately with completion scheduled in 2022. The three single-shaft power trains for the facility will be provided by General Electric Company utilizing 7HA.02 gas-fired turbines. The Guernsey Power Station is being jointly developed by Caithness Energy, L.L.C. and Apex Power Group, LLC.
A copy of Argan’s press release is attached to this report as Exhibit 99.1 and is incorporated herein by reference.
Item 9.01. Financial Statements and Exhibits.
(d) Exhibits
Exhibit No. |
| Description |
|
|
|
99.1 |
| Press release issued by Argan on August 29, 2019 |
EXHIBIT INDEX
Exhibit No. |
| Description |
|
|
|
99.1 |
|
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the Registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
| ARGAN, INC. | |
|
|
|
Date: August 29, 2019 | By: | /s/ David H. Watson |
|
| David H. Watson |
|
| Senior Vice President, Chief Financial Officer, |