Management’s Discussion and Analysis
For the three months and year ended December 31, 2020
Q4 and 2020 Analysis
Production
During Q4 2020, Los Filos produced 13,615 oz of gold (Q3 2020 – 17,530 oz) and sold 13,740 oz (Q3 2020 – 19,757 oz), realizing revenue of $26.4 million (Q3 2020 – $37.2 million) for the Quarter, at an AISC of $1,271 per oz (Q3 2020 – $1,368 per oz) and an average realized price of $1,932 per oz (Q3 2020 – $1,878 per oz).
Mining and development activities were suspended in early September due to a blockade from members of one of the three primary communities from which the mine draws its workforce. The blockade was removed in late December and access to the mine was restored. The Company began a staged restart following removal of the blockade and poured 13,615 oz in December from the gold adsorbed in carbon during the suspension.
Los Filos 2020 production attributable to Equinox Gold totalled 58,453 oz of gold. Production was lower than expected as the result of a temporary suspension of mining activities for the majority of Q2 2020 in compliance with government-mandated restrictions related to COVID-19, and again from the community blockade from early September through late December 2020. The suspensions also interrupted development activities, delaying access to higher-grade ore that was expected to contribute to 2020 production. Los Filos guidance was withdrawn on November 9, 2020, since the Company could not forecast timing for the restart of operations.
Los Filos AISC for 2020 was $1,189 per oz of gold sold, reflecting the reduction in ounces produced. Costs directly associated with the temporary suspension and restart of activities were recorded as care and maintenance and excluded from AISC.
During 2020 Los Filos had one lost-time injury, achieving LTIFR and TRIFR of 0.3 and 4.4, respectively.
Exploration and development
All on-site development and exploration activities were suspended for the majority of Q2 2020 and from September through December. Exploration activities recommenced in January 2021.
During Q4 2020, as a result of the suspension, sustaining capital expenditures were only $3.2 million, primarily for equipment refurbishments. The Company continued to advance technical studies related to the planned expansion, as described in Development Projects below. Non-sustaining capital expenditures of $2.9 million during the Quarter related primarily to off-site engineering, design and feasibility study work.
During 2020, the Company spent $11.2 million of sustaining capital expenditures and $16.5 million of non-sustaining capital, both related primarily to stripping of the Guadalupe open pit.
Outlook
Representatives from Los Filos continue to meet regularly with community leaders to reach consensus on the remaining items related to benefits provided under the community’s social collaboration agreement.
Los Filos production for 2021 is estimated at 170,000 to 190,000 oz of gold, with production weighted heavily toward the second half of the year. Production will gradually increase during Q1 2021 as mining activities and leaching ramp up following the December restart, and also increase quarter-over-quarter as development activities provide access to higher-grade ore from the Guadalupe open pit. Additional ore will be sourced from the Bermejal underground deposit upon commencement of underground development, which is on hold pending finalization of the community social collaboration agreement.
Cash costs and AISC are expected to be higher at the start of the year and lower in H2 2021 as grade and production increases, with full-year cost guidance estimated at cash costs of $1,125 to $1,200 per oz sold, with AISC of $1,330 to $1,390 per oz sold.
Capital investments at Los Filos during 2021 will set the stage for production growth and mine life extension, with a total budget of $133 million for the year. AISC includes $38 million of sustaining capital, with $13 million allocated for fleet refurbishment and processing equipment, $9 million for development at the Los Filos underground mine and $13 million for capitalized stripping of the Los Filos and Guadalupe open pits.
Non-sustaining capital of $95 million relates to the expansion project and was in part deferred from 2020, including $48 million for Bermejal underground development, $10 million for pre-stripping of the Guadalupe open pit and $25 million for fleet rebuilds and new equipment. In addition, $9 million is directed to exploration and Los Filos underground development.