Exhibit B.1
Supplier Milestones
1.
Commence achieving Ex Works status for Towers.
2.
Commence shipping of Towers.
3.
Commence achieving Ex Works status for Blade Sets, Turbine Nacelles and Hubs.
4.
Commence shipping of Blade Sets, Turbine Nacelles and Hubs.
5.
Complete deliveries of Towers.
6.
Complete deliveries of Blade Sets, Turbine Nacelles and Hubs.
7.
Completion of Commissioning of Wind Turbines.
8.
SCADA Completion.
9.
Final Completion.
Exhibit B.2
Project Schedule
Project Milestone | Responsible Party | Completion Date |
Provide storage and laydown areas and access thereto at Project Site for Turbine Equipment and tools | Buyer | 4 weeks prior to the first Anticipated Delivery Date |
Completion of site calibration for Power Curve Testing | Buyer | Prior to erection of first Tower |
Anticipated Delivery Dates Group 1: Qty. Nine (9) Wind Turbines and Towers | Supplier | Group 1: Week of 8/27/07 Group 2: Week of 9/10/07 |
Guaranteed Delivery Dates Group 1: Qty. Nine (9) Wind Turbines and Towers Group 2: Qty. Nine (9) Wind Turbines and Towers | Supplier | Group 1: 9/28/07 Group 2: 10/12/07 |
Permanent Grid Energization | Buyer | 10/1/07 |
Commence erection and installation of Wind Turbines | Buyer | Week of 10/1/07 |
Complete installation of Fiber Optic Cable to Server | Buyer | On or before Mechanical Completion of the first Wind Turbine |
Mechanical Completion of Wind Turbines Group 1: Qty. Nine (9) Wind Turbines Group 2: Qty. Nine (9) Wind Turbines | Buyer | Group 1: 10/12/07 Group 2: 10/26/07 |
Commissioning Completion of Wind Turbines | Supplier | Seven (7) Business Days after Mechanical Completion of the relevant Wind Turbine, subject to Section 3.9 of the Agreement |
Terminate SCADA fiber optic cables | Supplier | Not later than five (5) days after Commissioning Completion of the relevant Wind Turbine |
Connectivity of SCADA fiber optic cables | Buyer | Not later than five (5) days after Commissioning Completion of the relevant Wind Turbine or string of Wind Turbines required for connectivity |
SCADA Connectivity to Wind Turbine | Supplier | Not later than ten (10) days after Connectivity of SCADA fiber optic cables but conditioned on connectivity through other Wind Turbine on the string |
SCADA Completion | Supplier | 45 days after Commissioning Completion of the last Wind Turbine |
Final Completion | Supplier | 60 days after Commissioning Completion of the last Wind Turbine |
Completion of Punchlist Items | Supplier | 60 days after Final Completion |