UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
Form 6-K
REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE
13a-16 OR 15d-16 UNDER
THE SECURITIES EXCHANGE ACT OF 1934
For the month of April 2021
Commission File Number 001-13314
Huaneng Power International, Inc.
(Translation of registrant’s name into English)
Huaneng Power International, Inc.
Huaneng Building,
6 Fuxingmennei Street,
Xicheng District,
Beijing, 100031 PRC
(Address of principal executive office)
Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F. Form 20-F x Form 40-F ¨
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): ¨
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ¨
This Form 6-K consists of an announcement on electricity sold within China for the first quarter of 2021 of Huaneng Power International, Inc.(the "Registrant"), made by the Registrant on April 16, 2021.
Hong Kong Exchanges and Clearing Limited and The Stock Exchange of Hong Kong Limited take no responsibility for the contents of this announcement, make no representation as to its accuracy or completeness and expressly disclaim any liability whatsoever for any loss howsoever arising from or in reliance upon the whole or any part of the contents of this announcement.
(Stock Code: 902)
ANNOUNCEMENT ON ELECTRICITY SOLD WITHIN CHINA
FOR THE FIRST QUARTER OF 2021
This announcement is made pursuant to Rule 13.10B of the Rules Governing the Listing of Securities on The Stock Exchange of Hong Kong Limited.
According to the preliminary statistics of Huaneng Power International, Inc. (the “Company”), for the first quarter of 2021, the Company’s total electricity sold by power plants within China on consolidated basis amounted to 105.009 billion KWh, representing an increase of 30.20% over the same period last year. For the first quarter of 2021, the Company’s average on-grid electricity settlement price for its power plants within China amounted to RMB419.98 per MWh, representing a decrease of 0.56% over the same period last year. For the first quarter of 2021, the ratio of Company’s market based electricity sold reached 57.34%, representing an increase of 24.07 percentage points over the same period last year.
The increase in the Company’s electricity was mainly attributable to the significant year-on-year rise in power generation side driven by an increased electricity demand in the first quarter of 2021. In addition, given that the first quarter is the heating season for northern China, the Company’s thermal power units saw a relatively large increase in utilization hours which further contributed to this growth.
The electricity sold (in billion kWh) of the Company, by regions, is listed below:
| | Electricity Sold | |
Region | | | January to March 2021 | | | | Year-on-Year Change | |
Heilongjiang Province | | | 2.908 | | | | 4.81 | % |
Coal-fired | | | 2.586 | | | | 3.94 | % |
Wind-power | | | 0.290 | | | | 13.92 | % |
PV | | | 0.032 | | | | -0.64 | % |
Jilin Province | | | 2.267 | | | | 2.26 | % |
| | Electricity Sold | |
Region | | | January to March 2021 | | | | Year-on-Year Change | |
Coal-fired | | | 1.792 | | | | -5.59 | % |
Wind-power | | | 0.332 | | | | 32.75 | % |
Hydro-power | | | 0.000 | | | | -99.79 | % |
PV | | | 0.063 | | | | 303.69 | % |
Biomass power | | | 0.080 | | | | 79.96 | % |
Liaoning Province | | | 4.200 | | | | 10.63 | % |
Coal-fired | | | 4.044 | | | | 10.84 | % |
Wind-power | | | 0.119 | | | | 16.11 | % |
Hydro-power | | | 0.000 | | | | -94.57 | % |
PV | | | 0.036 | | | | -4.89 | % |
Inner Mongolia | | | 0.068 | | | | 41.44 | % |
Wind-power | | | 0.068 | | | | 41.44 | % |
Hebei Province | | | 2.766 | | | | 17.53 | % |
Coal-fired | | | 2.634 | | | | 18.57 | % |
Wind-power | | | 0.122 | | | | 3.35 | % |
PV | | | 0.010 | | | | -27.48 | % |
Gansu Province | | | 4.398 | | | | 16.48 | % |
Coal-fired | | | 3.754 | | | | 15.18 | % |
Wind-power | | | 0.644 | | | | 24.66 | % |
Ningxia | | | 0.004 | | | | -12.07 | % |
PV | | | 0.004 | | | | -12.07 | % |
Beijing | | | 2.357 | | | | 23.22 | % |
Coal-fired | | | 0.648 | | | | 3.60 | % |
Combined Cycle | | | 1.710 | | | | 32.74 | % |
Tianjin | | | 1.639 | | | | -10.23 | % |
Coal-fired | | | 1.160 | | | | -11.53 | % |
Combined Cycle | | | 0.477 | | | | -7.28 | % |
PV | | | 0.003 | | | | 253.70 | % |
Shanxi Province | | | 2.871 | | | | 10.55 | % |
| | Electricity Sold | |
Region | | | January to March 2021 | | | | Year-on-Year Change | |
Coal-fired | | | 1.441 | | | | 3.51 | % |
Combined Cycle | | | 1.175 | | | | 1.38 | % |
Wind-power | | | 0.073 | | | | – | |
PV | | | 0.182 | | | | 297.37 | % |
Shandong Province | | | 19.391 | | | | 15.01 | % |
Coal-fired | | | 18.863 | | | | 13.70 | % |
Wind-power | | | 0.370 | | | | 97.59 | % |
PV | | | 0.123 | | | | 47.40 | % |
Biomass power | | | 0.035 | | | | – | |
Henan Province | | | 5.285 | | | | 38.84 | % |
Coal-fired | | | 4.334 | | | | 20.46 | % |
Combined Cycle | | | 0.020 | | | | -33.83 | % |
Wind-power | | | 0.925 | | | | 436.54 | % |
PV | | | 0.006 | | | | 1.65 | % |
Jiangsu Province | | | 10.218 | | | | 32.16 | % |
Coal-fired | | | 7.889 | | | | 26.64 | % |
Combined Cycle | | | 1.212 | | | | 39.00 | % |
Wind-power | | | 1.058 | | | | 74.40 | % |
PV | | | 0.059 | | | | 150.89 | % |
Shanghai | | | 5.367 | | | | 44.83 | % |
Coal-fired | | | 5.159 | | | | 59.24 | % |
Combined Cycle | | | 0.201 | | | | -56.86 | % |
PV | | | 0.007 | | | | – | |
Chongqing | | | 3.665 | | | | 82.78 | % |
Coal-fired | | | 2.830 | | | | 71.87 | % |
Combined Cycle | | | 0.772 | | | | 147.92 | % |
Wind-power | | | 0.064 | | | | 33.62 | % |
Zhejiang Province | | | 6.516 | | | | 47.08 | % |
Coal-fired | | | 6.339 | | | | 45.09 | % |
| | Electricity Sold | |
Region | | | January to March 2021 | | | | Year-on-Year Change | |
Combined Cycle | | | 0.167 | | | | 230.68 | % |
PV | | | 0.010 | | | | -5.31 | % |
Hubei Province | | | 4.670 | | | | 39.29 | % |
Coal-fired | | | 4.448 | | | | 41.65 | % |
Wind-power | | | 0.179 | | | | 16.64 | % |
Hydro-power | | | 0.039 | | | | -29.85 | % |
PV | | | 0.005 | | | | 10.54 | % |
Hunan Province | | | 2.706 | | | | 32.83 | % |
Coal-fired | | | 2.476 | | | | 39.34 | % |
Wind-power | | | 0.175 | | | | 14.14 | % |
Hydro-power | | | 0.046 | | | | -53.98 | % |
PV | | | 0.009 | | | | 24.00 | % |
Jiangxi Province | | | 5.154 | | | | 25.32 | % |
Coal-fired | | | 4.881 | | | | 25.25 | % |
Wind-power | | | 0.191 | | | | -4.50 | % |
PV | | | 0.082 | | | | 421.83 | % |
Anhui Province | | | 1.536 | | | | 29.33 | % |
Coal-fired | | | 1.255 | | | | 12.82 | % |
Wind-power | | | 0.250 | | | | 232.11 | % |
Hydro-power | | | 0.031 | | | | – | |
Fujian Province | | | 4.248 | | | | 72.39 | % |
Coal-fired | | | 4.245 | | | | 72.45 | % |
PV | | | 0.003 | | | | 13.78 | % |
Guangdong Province | | | 7.174 | | | | 122.32 | % |
Coal-fired | | | 6.262 | | | | 94.36 | % |
Combined Cycle | | | 0.906 | | | | – | |
PV | | | 0.006 | | | | 17.77 | % |
Guangxi | | | 0.184 | | | | 59.46 | % |
Combined Cycle | | | 0.105 | | | | 58.57 | % |
| | Electricity Sold | |
Region | | | January to March 2021 | | | | Year-on-Year Change | |
Wind-power | | | 0.079 | | | | 60.66 | % |
Yunnan Province | | | 3.048 | | | | 98.60 | % |
Coal-fired | | | 2.903 | | | | 117.43 | % |
Wind-power | | | 0.145 | | | | -26.45 | % |
Hydro-power | | | 0.000 | | | | -90.44 | % |
Guizhou Province | | | 0.071 | | | | -13.18 | % |
Wind-power | | | 0.054 | | | | -33.40 | % |
PV | | | 0.017 | | | | 2385.10 | % |
Hainan Province | | | 2.299 | | | | -14.63 | % |
Coal-fired | | | 2.149 | | | | -17.51 | % |
Combined Cycle | | | 0.089 | | | | 176.40 | % |
Wind-power | | | 0.021 | | | | -17.78 | % |
Hydro-power | | | 0.017 | | | | 123.24 | % |
PV | | | 0.024 | | | | 4.12 | % |
Total | | | 105.009 | | | | 30.20 | % |
For the first quarter of 2021, the power generation of Tuas Power Limited in Singapore, which is wholly-owned by the Company, accounted for a market share of 20.6% in Singapore, representing a decrease of 0.6 percentage point over the same period last year.
The Company’s new projects which have commenced operation in the first quarter of 2021 are as follows:
(in MW)
Type | | | controlled installed capacity | | | equity-based installed capacity | |
Wind-power | | | | 421.55 | | | | 383.96 | |
Biomass | | | | 30.00 | | | | 24.00 | |
Total | | | | 451.55 | | | | 407.96 | |
In addition, the installed capacity of some of the power plants in which the Company has equity interests changed in the first quarter of 2021.
Based on the above, as of 31 March 2021, the Company had a controlled installed generation capacity of 113,805MW and equity-based installed generation capacity of 99,570MW.
By order of the Board
Huaneng Power International, Inc.
Huang Chaoquan
Company Secretary
As of the date of the announcement, the directors of the Company are:
Zhao Keyu (Executive Director) | Xu Mengzhou (Independent Non-executive Director) |
Zhao Ping (Executive Director) | Liu Jizhen (Independent Non-executive Director) |
Huang Jian (Non-executive Director) | Xu Haifeng (Independent Non-executive Director) |
Wang Kui (Non-executive Director) | Zhang Xianzhi (Independent Non-executive Director) |
Lu Fei (Non-executive Director) | Xia Qing (Independent Non-executive Director) |
Teng Yu (Non-executive Director) | |
Mi Dabin (Non-executive Director) | |
Cheng Heng (Non-executive Director) | |
Li Haifeng (Non-executive Director) | |
Lin Chong (Non-executive Director) | |
Beijing, the PRC
16 April 2021
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
| HUANENG POWER INTERNATIONAL, INC. |
| |
| By: | /s/ Huang Chaoquan |
| Name: | Huang Chaoquan |
| Title: | Company Secretary |
| |
Date: April 16, 2021 | |